Nebius Independence AI Factory
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
- Utility
- Independence Power & Light · Independence Power Partners · Southwest Power Pool
Nebius has begun constructing a multi-building AI factory in Independence, Missouri. The approved campus may ultimately use a 1.2 GW power envelope, but initial power and later generation remain separate future steps rather than live IT capacity.
Capacity
Facility power potential
Planned / design or future potential1,200 MW
Full-build power and campus potential · Phase
Phase scope; not a whole-site figure
SourceInitial power availability target
Planned / design or future potential200 MW
Initial campus construction · Phase
Phase scope; not a whole-site figure
SourcePlanned offsite generation
Planned / design or future potential800 MW
Full-build power and campus potential · Phase
Phase scope; not a whole-site figure
SourceFuture onsite generation
Planned / design or future potential400 MW
Full-build power and campus potential · Phase
Phase scope; not a whole-site figure
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Financial-plan approval is distinct from construction permits.
4 buildings
Four-building campus concept; no building-level schedule or capacity allocation is published.
4 buildings
Do not treat as delivered power, operating IT load or committed customer capacity.
Milestones (4)
Mar 2, 2026 · Recorded actual event
Completed · Permit approved
Source not linkedMay 12, 2026 · Recorded actual event
Completed · Construction started
Source not linkedJul 6, 2026 · Recorded actual event
Completed · Permit filed
Source not linked2026 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- Nebius breaks ground on gigawatt-scale AI factory in Independence, Missouri · May 12, 2026 · Corroborating
Operator (1)
- Nebius secures approval for its first gigawatt-scale AI factory · Mar 3, 2026 · Primary
Operator (1)
- Independence, Missouri AI factory project page · Corroborating
Developer
Sources by role
Developer (1)
- Nebius breaks ground on gigawatt-scale AI factory in Independence, Missouri · May 12, 2026 · Primary
Other participants (6)
Contractor
Sources by role
Contractor (1)
- Nebius breaks ground on gigawatt-scale AI factory in Independence, Missouri · May 12, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Nebius Data Center FAQs · Primary
Utility provider
Sources by role
Utility provider (1)
Utility provider (1)
- Nebius Data Center FAQs · Corroborating
Government authority
Sources by role
Government authority (1)
- Nebius breaks ground on gigawatt-scale AI factory in Independence · May 12, 2026 · Primary
Utility provider
Sources by role
Utility provider (1)
- Nebius Data Center FAQs · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Debt financing
Amount not disclosedMar 2, 2026
Approved municipal financing/ownership mechanism supporting tax abatement; exact bond authorization, issuance amount and purchaser terms not captured.
Parties & sources
City of Independence (Other / Municipal issuer and lessor context) · Nebius (Borrower)
Sources (2)
Incentives
Property tax abatement
for 20 years
Approved · City of Independence
Projected PILOT payments above USD 650 million over 20 years; property-tax rate/abatement schedule not captured in reviewed pages.
Sales tax exemption
Approved · City of Independence
Sales/use tax exemption described as part of approved Chapter 100 mechanism; eligible purchases and dollar value not captured.
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (5)
Under construction
closed loop cooling; under construction.
Planned or represented
200 MW
utility service initial — 200 MW; forecast h2 2026.
Planned or represented
800 MW
offsite generation supply — 800 MW; planned.
Potential or planned
400 MW
onsite generation — 400 MW; future potential.
Planned or represented
The operator describes emergency generators for controlled shutdown rather than continuous operation of the full facility. The cited description does not establish a MW rating or commissioned installation.
Project map
Building · Under review
Public-source research. Plans may change. See Evidence for sources and qualifications.