Nebius Independence AI Factory

Independence, Missouri, United StatesUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026
Utility
Independence Power & Light · Independence Power Partners · Southwest Power Pool

Nebius has begun constructing a multi-building AI factory in Independence, Missouri. The approved campus may ultimately use a 1.2 GW power envelope, but initial power and later generation remain separate future steps rather than live IT capacity.

Capacity

Facility power potential

Planned / design or future potential

1,200 MW

Full-build power and campus potential · Phase

Phase scope; not a whole-site figure

Source

Initial power availability target

Planned / design or future potential

200 MW

Initial campus construction · Phase

Phase scope; not a whole-site figure

Source

Planned offsite generation

Planned / design or future potential

800 MW

Full-build power and campus potential · Phase

Phase scope; not a whole-site figure

Source

Future onsite generation

Planned / design or future potential

400 MW

Full-build power and campus potential · Phase

Phase scope; not a whole-site figure

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Chapter 100 approval and site enablingAnnounced or preconstruction

Financial-plan approval is distinct from construction permits.

Initial campus constructionUnder construction

4 buildings

Four-building campus concept; no building-level schedule or capacity allocation is published.

Full-build power and campus potentialPlanned

4 buildings

Do not treat as delivered power, operating IT load or committed customer capacity.

Milestones (4)
City Council approves Chapter 100 plan

Mar 2, 2026 · Recorded actual event

Completed · Permit approved

Source not linked
Nebius begins first-phase construction

May 12, 2026 · Recorded actual event

Completed · Construction started

Source not linked
Nebius excluded from temporary new-application moratorium

Jul 6, 2026 · Recorded actual event

Completed · Permit filed

Source not linked
Initial 200 MW power target

2026 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Nebius

Operator

Sources by role
Other participants (6)
City of Independence

Government authority

Sources by role
Government authority (1)
Independence Power & Light

Utility provider

Sources by role
Utility provider (1)
Utility provider (1)
Independence Power Partners

Utility provider

Sources by role
Utility provider (1)
Missouri Department of Economic Development

Government authority

Sources by role
Government authority (1)
Southwest Power Pool

Utility provider

Sources by role
Utility provider (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Pilot payments projected

Transaction scope

$>650000000

Source

Financing records

Debt financing

Amount not disclosed

Mar 2, 2026

Approved municipal financing/ownership mechanism supporting tax abatement; exact bond authorization, issuance amount and purchaser terms not captured.

Parties & sources

City of Independence (Other / Municipal issuer and lessor context) · Nebius (Borrower)

Incentives

Property tax abatement

for 20 years

Approved · City of Independence

Projected PILOT payments above USD 650 million over 20 years; property-tax rate/abatement schedule not captured in reviewed pages.

Sales tax exemption

Approved · City of Independence

Sales/use tax exemption described as part of approved Chapter 100 mechanism; eligible purchases and dollar value not captured.

Site & development

Site area

Reported rounded

400 acre

Source

Planned building count

Design

4 building

Initial campus construction · Phase

Source

Construction jobs

Reported rounded

1,200 job

Source

Gross floor area

Reported rounded

2,250,000 sq. ft.

Conflicting public evidence

Source

Gross floor area

Reported rounded

2,500,000 sq. ft.

Conflicting public evidence

Source

Technical specifications

Cooling system

Design

Closed loop cooling

Source

Initial water fill per 200mw

Reported rounded

1,000,000 US gallon

Source

Annual water use

Reported rounded

400000-640000 US gallon per year

Conflicting public evidence

Source

Annual water use

Reported rounded

450000-600000 US gallon per year

Conflicting public evidence

Source

Additional project facts

Project status

Actual

Under construction

Source

Permanent jobs full operation

Reported rounded

130 job

Conflicting public evidence

Source

Permanent jobs full operation

Reported rounded

125 job

Conflicting public evidence

Source

Pilot term

Actual

20

Source

Build duration

Reported rounded

5-7 year

Full-build power and campus potential · Phase

Conflicting public evidence

Source

Build duration

Reported rounded

3-5 year

Full-build power and campus potential · Phase

Conflicting public evidence

Source

Data center moratorium applies

Actual

False

Source

Infrastructure & permits

Technical details (5)
Closed loop cooling

Under construction

closed loop cooling; under construction.

Utility service

Planned or represented

200 MW

utility service initial — 200 MW; forecast h2 2026.

Electric grid

Planned or represented

800 MW

offsite generation supply — 800 MW; planned.

Onsite generation

Potential or planned

400 MW

onsite generation — 400 MW; future potential.

Onsite generation

Planned or represented

The operator describes emergency generators for controlled shutdown rather than continuous operation of the full facility. The cited description does not establish a MW rating or commissioned installation.

Building · Under review

Nebius Independence campus

City of Independence

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.