Scope and capacity
Alcalá de Henares city reported groundbreaking for Nabiax’s ADC3 building on September 18, 2026. This adds a construction milestone to the campus history, not newly commissioned IT capacity or an additive full-campus capacity total. Campus boundary containing ADC1, ADC2 and ADC3, previously proposed and now reported at groundbreaking; existing 22.3 MW, 100 MW scalability and companywide 140 MW objective remain separate scopes.
Headline: 100 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Built phase count · 2 phases
Source report · Nabiax Alcalá Data Center Campus (Project)
Claim 44904 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Current operating IT capacity · 22.3 MW IT
Actual · Nabiax Alcalá Data Center Campus (Project)
Claim 44905 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Not included in reviewed operating IT capacity
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Medium term scalable IT capacity · 100 MW IT
Planned / design or future potential · Nabiax Alcalá Data Center Campus (Project)
Claim 44906 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Nabiax starts Alcalá data center campus expansion
Nabiax · Document date: Oct 22, 2021 · Primary
Source reference: SRC-2478 · Company announcement · Recorded authority: Party primary
Source URL
https://nabiax.com/en/nabiax-starts-alcala-data-center-campus-expansion-with-its-100-mw-it-will-be-spains-biggest/
https://nabiax.com/en/nabiax-starts-alcala-data-center-campus-expansion-with-its-100-mw-it-will-be-spains-biggest/
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Current IT space · 10,000 square meters
Source report · Nabiax Alcalá Data Center Campus (Project)
Claim 44907 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Renewable electricity claim · 100 percent
Source report · Nabiax Alcalá Data Center Campus (Project)
Claim 44908 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Forecast permanent jobs · 200 jobs
Source report · Nabiax Alcalá Data Center Campus (Project)
Claim 44931 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Nabiax invertirá 800 millones en la ampliación de sus centros de datos en España
Cinco Días · Document date: Aug 4, 2026 · Primary
Source reference: SRC-2480
Source URL
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
Counterparties and capital
Aermont Capital · Owner · CMP-1145
Asterion Industrial Partners · Owner · CMP-1146
Nabiax · Operator · CMP-1144
Telefónica · Owner · CMP-1147
€320,000,000 · Jan 1, 2021
Nabiax platform financing linked to ESG indicators; retained as context and not allocated to Alcalá or ADC3.
Nabiax (Borrower / financed platform)
Sources (1)
- Telefónica 2021 Results · Feb 24, 2022
Financing record 128; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.