Cartis diligence evidence schedule
Nabiax Alcalá ADC3
PRJ-0467 · Site · Alcalá de Henares / Madrid, MD, Spain
Record last updated Oct 28, 2026
Scope and capacity
Alcalá de Henares city reported that groundbreaking for Nabiax's third data-center building took place on September 18, 2026. This marks construction progress, not commissioning or delivery of the planned IT capacity. Nabiax Alcalá ADC3 is the third building, previously proposed and now reported at groundbreaking, marketed with 100 MW secured IT power; included within the campus scalability figure without a disclosed power-allocation bridge.
Headline: 100 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (9)
Physical building order · 3 building
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44922 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Spain's Nabiax to expand Madrid data center campus
DatacenterDynamics · Document date: Aug 10, 2026 · Primary
Source reference: SRC-2479 · News report
Source URL
https://www.datacenterdynamics.com/en/news/spains-nabiax-to-expand-madrid-data-center-campus/
https://www.datacenterdynamics.com/en/news/spains-nabiax-to-expand-madrid-data-center-campus/
- Nabiax invertirá 800 millones en la ampliación de sus centros de datos en España
Cinco Días · Document date: Aug 4, 2026 · Primary
Source reference: SRC-2480
Source URL
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
Secured IT power design claim · 100 MW IT
Planned / design or future potential · Nabiax Alcalá ADC3 (Project)
Claim 44923 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- ADC3 — The large-scale hyperscaler opportunity in Spain
DatacenterDynamics / Nabiax · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2481 · Recorded authority: Party primary
Source URL
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
Additional power requested · 110 MW
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44924 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- ADC3 — The large-scale hyperscaler opportunity in Spain
DatacenterDynamics / Nabiax · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2481 · Recorded authority: Party primary
Source URL
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
Liquid cooling design share · 100 percent
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44925 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- ADC3 — The large-scale hyperscaler opportunity in Spain
DatacenterDynamics / Nabiax · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2481 · Recorded authority: Party primary
Source URL
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
Design PUE · 1.2 PUE
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44926 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- ADC3 — The large-scale hyperscaler opportunity in Spain
DatacenterDynamics / Nabiax · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2481 · Recorded authority: Party primary
Source URL
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
Design water consumption · 0 operational water
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44927 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- ADC3 — The large-scale hyperscaler opportunity in Spain
DatacenterDynamics / Nabiax · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2481 · Recorded authority: Party primary
Source URL
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
Renewable energy design claim · 100 percent
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44928 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- ADC3 — The large-scale hyperscaler opportunity in Spain
DatacenterDynamics / Nabiax · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2481 · Recorded authority: Party primary
Source URL
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
https://www.datacenterdynamics.com/en/whitepapers/adc3-the-large-scale-hyperscaler-opportunity-in-spain/
Announced investment plan · €800 million
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44929 · Recorded claim type: Not stated · Review: Approved · Claim date: Aug 4, 2026
- Spain's Nabiax to expand Madrid data center campus
DatacenterDynamics · Document date: Aug 10, 2026 · Primary
Source reference: SRC-2479 · News report
Source URL
https://www.datacenterdynamics.com/en/news/spains-nabiax-to-expand-madrid-data-center-campus/
https://www.datacenterdynamics.com/en/news/spains-nabiax-to-expand-madrid-data-center-campus/
- Nabiax invertirá 800 millones en la ampliación de sus centros de datos en España
Cinco Días · Document date: Aug 4, 2026 · Primary
Source reference: SRC-2480
Source URL
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
Forecast construction jobs · 1,000 jobs
Source report · Nabiax Alcalá ADC3 (Project)
Claim 44930 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Nabiax invertirá 800 millones en la ampliación de sus centros de datos en España
Cinco Días · Document date: Aug 4, 2026 · Primary
Source reference: SRC-2480
Source URL
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
https://cincodias.elpais.com/companias/2026-08-04/nabiax-invertira-800-millones-en-la-ampliacion-de-sus-centros-de-datos-en-espana.html
Counterparties and capital
Nabiax · Developer · CMP-1144
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.