Microsoft Villamayor de Gallego Data Center Campus

Villamayor de Gallego, Aragon, SpainUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Microsoft Villamayor de Gallego Data Center Campus is in Villamayor de Gallego, Aragon, ES and is a data center campus with under construction status.

Program relationships

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Early worksUnder construction

Secondary report of initial earthmoving; full building construction not independently confirmed.

Milestones (2)
Villamayor DIGA declared

Jul 2024 · Recorded actual event

Completed · Permit approved

Source not linked
Initial earthmoving reported

Jul 7, 2026 · Recorded actual event

Completed · Construction started

Source not linked

Participants

Microsoft

Developer

Sources by role
Developer (1)
Developer (1)
Other participants (2)
Government of Aragon

Government authority

Sources by role
Government authority (1)
Government authority (1)
Government authority (1)
Government authority (1)
Government authority (1)
Municipality of Villamayor de Gallego

Government authority

Sources by role
Government authority (1)

Site & development

Site area

Actual

80.67 hectares

Source

Additional project facts

Early earthworks status

Actual

Initial earthmoving reported

Source

Infrastructure & permits

Other · Issued

Villamayor de Gallego campus

Government of Aragon

Nov 1, 2025

Sources (3)

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
Microsoft La Muela Data Center Campus

Preconstruction · La Muela / Centrovia, Aragon, Spain

Shared participant: Government of Aragon · Shared participant: Microsoft · Same market: Aragon, Spain

Compare in a collection
Microsoft Zaragoza PTR Data Center Campus

Preconstruction · Zaragoza / PTR Lopez Soriano, Aragon, Spain

Shared participant: Government of Aragon · Shared participant: Microsoft · Same market: Aragon, Spain

Compare in a collection
Microsoft Zaragoza Puerto Venecia Data Center Campus

Preconstruction · Zaragoza / Puerto Venecia / Z-40, Aragon, Spain

Shared participant: Government of Aragon · Shared participant: Microsoft · Same market: Aragon, Spain

Compare in a collection
AWS Europe (Spain) / Aragon Region

Status under review · Zaragoza / Huesca, Aragon, Spain

Shared participant: Government of Aragon · Same market: Aragon, Spain

Compare in a collection