Microsoft Southern Finland Data Center Region

Espoo / Kirkkonummi / Vihti, Uusimaa, FinlandStatus under reviewProgram
Evidence
Headline capacity
See constituent sites
Updated
Oct 28, 2026

On April 28, 2026, Microsoft announced a decision to proceed with second-phase construction and reported permits at all three Southern Finland campuses. It targeted completion of first-phase construction around the end of 2026 and beginning of 2027, followed by commissioning preparations and a separate opening announcement. This does not establish that the cloud region is open or that second-phase construction had started at every campus. Microsoft Southern Finland Data Center Region is in Espoo / Kirkkonummi / Vihti, Uusimaa, FI and is a program under development.

Constituent sites / phases

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (2)
Southern Finland region announced

Mar 17, 2022 · Recorded actual event

Completed · Announced

Source not linked
Fortum data center waste-heat integration begins

2027 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Microsoft

Developer

Sources by role
Developer (1)
Developer (1)
Developer (1)
Other participants (1)
Fortum Oyj

Contractor

Sources by role
Contractor (1)
Contractor (1)

Capital & incentives

Capital claims

Reported 2025 operational activity

Source report

€37 million

Source

Construction activity since 2023

Source report

€200 million

Source

Projected 2026 2028 economic activity

Source report

€1.29 billion

Source

Projected 2028 operational activity

Source report

€143 million

Source

Site & development

Projected 2026 2028 local construction related jobs

Actual

12,650 jobs

Source

Additional project facts

Physical campus count

Actual

3 campuses

Source

Projected 2028 local jobs

Actual

725 jobs

Source

Infrastructure & permits

Technical details (3)
Heat reuse

Partially operational

€225 million infrastructure investment

Shared program connects the Espoo and Kirkkonummi campuses to Fortum heat-pump/district-heating infrastructure; Vihti is excluded.

Heat reuse

Potential or planned

75 percent

Approximately 75% of recoverable waste heat is expected to be used; this is a thermal-recovery share, not data center efficiency or IT load.

Heat reuse

Potential or planned

40 percent of annual network demand

Project could eventually provide about 40% of annual district-heat demand in the service area, which uses approximately 2 TWh per year.

Public-source research. Plans may change. See Evidence for sources and qualifications.