Meta–Reliance Jamnagar
- Planned critical IT
- 168 MW
- Updated
- Oct 28, 2026
- Utility
- Reliance planned utilities provider; upstream service arrangement not disclosed
Meta and Reliance confirmed a Jamnagar lease agreement in June 2026. Reliance will develop the facility and provide utilities, network connectivity and managed services. Meta's transaction counsel describes 168 MW of planned critical load; no operating IT load is established. Reliance forecast delivery within two years of June 10, 2026. Its later earnings commentary envisages the 168 MW together but withholds an exact commissioning date. Renewable power and desalinated-seawater cooling are plans, not measured performance. Reliance says it is proceeding on its balance sheet without disclosing a site amount. Parcel title, project permits and awarded incentives remain unverified.
Capacity
Planned 168 MW delivery sequencing
Planned / design or future potentialReliance envisages the 168 MW arriving together; not an achieved handover
SourcePlanned network connectivity
Planned / design or future potentialReliance to provide network connectivity; Jio fiber and western cable landing stations are regional context, not proven commissioned routes
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Participants
Developer lessor and planned managed services provider
Tenant and compute customer
Other participants (1)
Meta transaction legal counsel
Site & development
Land and SEZ status described by transaction counsel
Party description, not regulatory approvalProposed SEZ; exact facility parcel and notification linkage not established
SourceTechnical specifications
Additional project facts
Announced facility lease structure
AnnouncedReliance develops and leases capacity to Meta; lease price and term not disclosed
SourceAnnounced tenant and compute customer
AnnouncedMeta; facility managed services planned from Reliance
SourceDeveloper
AnnouncedReliance Industries; design, construction, utility management, network and managed services
SourceExact commissioning date
Forecast window, not achieved openingNot disclosed; June 10, 2026 release forecasts delivery within two years
SourceSeparate India renewable portfolio — not Jamnagar facility capacity
Renewable portfolio context not site capacityNearly 1 GW
SourceReliance own balance sheet delivery statement
Company statement, no quantified transactionGroup says it is proceeding on its own balance sheet; no site amount, instrument or financing close disclosed
SourceFacility delivery forecast
Company forecast not achievedWithin two years of June 10, 2026; exact commissioning date undisclosed
SourceSeparate Jio ownership and enterprise-AI venture context
Platform level transactionPrior Jio share investment and enterprise-AI venture do not establish Jamnagar facility financing or ownership
SourceInfrastructure & permits
Technical details (2)
Desalinated seawater design; actual use not established
desalinated seawater
Announced
Meta
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
Preconstruction · Jamnagar, Gujarat, India
Same locality: Jamnagar · Shared participant: Reliance Industries Limited