Cartis diligence evidence schedule

Meta Hyperion

PRJ-META-HYPERION-LA · Site · Richland Parish, Louisiana, United States

Captured 2026-09-06T04:12:50.290Z · Record last updated 2026-07-13

SHA-256: 33a3ddafef7752a0b725bcf6aefff0ae485c220647e431af67385c4505704e76

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Meta's Hyperion campus in Richland Parish began as a $10 billion, 4 million-square-foot project and was expanded in July 2026 to more than $50 billion, nearly 10 million square feet and 5 GW of IT capacity. Blue Owl-managed funds own 80% of the campus joint venture and Meta owns 20%.

Headline: 5,000 MW Planned / design

This record and the linked Hyperion record describe overlapping campus scope. Do not add their capacity figures or treat them as confirmed separate properties. Identity reconciliation is pending; both records and their evidence remain available.

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Original Investment · $10,000,000,000

announced · Meta Hyperion (project)

Claim AST-B1-024 · Review: Approved · Claim date: 2024-12-04

  1. Meta selects Northeast Louisiana for $10B AI data center

    Louisiana Economic Development · Document date: 2024-12-04 · Supports

    https://www.opportunitylouisiana.gov/news/meta-selects-northeast-louisiana-as-site-of-10-billion-artificial-intelligence-optimized-data-center-governor-jeff-landry-calls-investment-a-new-chapter-for-state

Current Investment Commitment · $50,000,000,000

announced current · Meta Hyperion (project)

Claim AST-B1-025 · Review: Approved · Claim date: 2026-07-13

  1. Meta commits more than $50B for North Louisiana project

    Louisiana Economic Development · Document date: 2026-07-13 · Supports

    https://www.opportunitylouisiana.gov/news/meta-commits-more-than-50-billion-for-north-louisiana-project-becoming-one-of-the-largest-data-centers-in-history

Original Gross Area · 4,000,000 sq. ft.

announced · Meta Hyperion (project)

Claim AST-B1-026 · Review: Approved · Claim date: 2024-12-04

  1. Meta selects Northeast Louisiana for $10B AI data center

    Louisiana Economic Development · Document date: 2024-12-04 · Supports

    https://www.opportunitylouisiana.gov/news/meta-selects-northeast-louisiana-as-site-of-10-billion-artificial-intelligence-optimized-data-center-governor-jeff-landry-calls-investment-a-new-chapter-for-state

Current Planned Gross Area · Nearly 10 million sq. ft.

Planned / design or future potential · Meta Hyperion (project)

Claim AST-B1-027 · Review: Approved · Claim date: 2026-07-13

Headline treatment: Separate claim, not added to the headline

  1. Meta commits more than $50B for North Louisiana project

    Louisiana Economic Development · Document date: 2026-07-13 · Supports

    https://www.opportunitylouisiana.gov/news/meta-commits-more-than-50-billion-for-north-louisiana-project-becoming-one-of-the-largest-data-centers-in-history

Planned It Capacity · 5 GW

Planned / design or future potential · Meta Hyperion (project)

Claim AST-B1-028 · Review: Approved · Claim date: 2026-07-13

Headline treatment: Selected headline

  1. Meta commits more than $50B for North Louisiana project

    Louisiana Economic Development · Document date: 2026-07-13 · Supports

    https://www.opportunitylouisiana.gov/news/meta-commits-more-than-50-billion-for-north-louisiana-project-becoming-one-of-the-largest-data-centers-in-history

Original Completion Forecast · 2030-12-31

forecast · Meta Hyperion (project)

Claim AST-B1-029 · Review: Approved With Followup · Claim date: 2024-12-04

  1. Meta selects Northeast Louisiana for $10B AI data center

    Louisiana Economic Development · Document date: 2024-12-04 · Supports

    https://www.opportunitylouisiana.gov/news/meta-selects-northeast-louisiana-as-site-of-10-billion-artificial-intelligence-optimized-data-center-governor-jeff-landry-calls-investment-a-new-chapter-for-state

Jv Total Development Cost · $27,000,000,000

contract scope · Meta Hyperion (project)

Claim AST-B1-030 · Review: Approved · Claim date: 2025-10-21

  1. Meta announces JV with Blue Owl funds to develop Hyperion

    Meta · Document date: 2025-10-21 · Supports

    https://investor.atmeta.com/investor-news/press-release-details/2025/Meta-Announces-Joint-Venture-with-Funds-Managed-by-Blue-Owl-Capital-to-Develop-Hyperion-Data-Center/default.aspx

Blue Owl Jv Interest · 80 percent

closed ownership · Meta Hyperion (project)

Claim AST-B1-031 · Review: Approved · Claim date: 2025-10-21

  1. Meta announces JV with Blue Owl funds to develop Hyperion

    Meta · Document date: 2025-10-21 · Supports

    https://investor.atmeta.com/investor-news/press-release-details/2025/Meta-Announces-Joint-Venture-with-Funds-Managed-by-Blue-Owl-Capital-to-Develop-Hyperion-Data-Center/default.aspx

Meta Jv Interest · 20 percent

closed ownership · Meta Hyperion (project)

Claim AST-B1-032 · Review: Approved · Claim date: 2025-10-21

  1. Meta announces JV with Blue Owl funds to develop Hyperion

    Meta · Document date: 2025-10-21 · Supports

    https://investor.atmeta.com/investor-news/press-release-details/2025/Meta-Announces-Joint-Venture-with-Funds-Managed-by-Blue-Owl-Capital-to-Develop-Hyperion-Data-Center/default.aspx

Blue Owl Cash Contribution · $7,000,000,000

closed financing · Meta Hyperion (project)

Claim AST-B1-033 · Review: Approved · Claim date: 2025-10-21

  1. Meta announces JV with Blue Owl funds to develop Hyperion

    Meta · Document date: 2025-10-21 · Supports

    https://investor.atmeta.com/investor-news/press-release-details/2025/Meta-Announces-Joint-Venture-with-Funds-Managed-by-Blue-Owl-Capital-to-Develop-Hyperion-Data-Center/default.aspx

Meta Distribution · $3,000,000,000

closed financing · Meta Hyperion (project)

Claim AST-B1-034 · Review: Approved · Claim date: 2025-10-21

  1. Meta announces JV with Blue Owl funds to develop Hyperion

    Meta · Document date: 2025-10-21 · Supports

    https://investor.atmeta.com/investor-news/press-release-details/2025/Meta-Announces-Joint-Venture-with-Funds-Managed-by-Blue-Owl-Capital-to-Develop-Hyperion-Data-Center/default.aspx

Operational Jobs · 800 jobs

forecast · Meta Hyperion (project)

Claim AST-B1-035 · Review: Approved With Followup · Claim date: 2026-07-13

  1. Meta commits more than $50B for North Louisiana project

    Louisiana Economic Development · Document date: 2026-07-13 · Supports

    https://www.opportunitylouisiana.gov/news/meta-commits-more-than-50-billion-for-north-louisiana-project-becoming-one-of-the-largest-data-centers-in-history

Local Infrastructure Commitment · $1,000,000,000

announced · Meta Hyperion (project)

Claim AST-B1-036 · Review: Approved · Claim date: 2026-07-13

  1. Meta commits more than $50B for North Louisiana project

    Louisiana Economic Development · Document date: 2026-07-13 · Supports

    https://www.opportunitylouisiana.gov/news/meta-commits-more-than-50-billion-for-north-louisiana-project-becoming-one-of-the-largest-data-centers-in-history

Counterparties and capital

Meta Platforms · Developer Construction Manager Property Manager Tenant

Laidley LLC · Initial Project Entity · CMP-0638

Evest LLC · Expansion Project Entity

Blue Owl Capital funds · 80 Percent Jv Owner · CMP-0008

Entergy Louisiana · Electric Utility · CMP-0640

Mortenson · General Contractor · CMP-0085

Turner Construction · General Contractor

DPR Construction · General Contractor

Original Investment

$10,000,000,000 · 2024-12-04

Financing record legacy-financing-AST-B1-024; claim-specific source links appear in the exhibit sources where published.

Current Investment Commitment

$50,000,000,000 · 2026-07-13

Financing record legacy-financing-AST-B1-025; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.