Meta Hyperion
Richland Parish, Louisiana, United StatesUnder construction
Capacity
5,000 MW
Planned / design
Lead participant
Blue Owl Capital funds
80 Percent Jv Owner
Last updated
Jul 13, 2026
Most recent public record update
About Meta Hyperion
Meta's Hyperion campus in Richland Parish began as a $10 billion, 4 million-square-foot project and was expanded in July 2026 to more than $50 billion, nearly 10 million square feet and 5 GW of IT capacity. Blue Owl-managed funds own 80% of the campus joint venture and Meta owns 20%.
Capacity
Planned / designOperating capacity—An operating IT-capacity figure has not been publicly disclosed.
DesignNearly 10 million sq. ft.Announced Current · Meta Hyperion
Design5,000 MWDesign Current · Meta Hyperion
Development
2 phases · 0 milestonesOriginal Laidley campusUnder Construction
Evest and 5 GW expansionPlanned And Under Regulatory Review
Infrastructure
No public infrastructure records are attached.
Project map
0 of 1 project point mappedInfrastructure facts
0
Mapped records
0
Capacity figures
0
No map point available
Facts & sources
Published claims and their source links.
Original Investment$10,000,000,000Announced
$10,000,000,000
Current Investment Commitment$50,000,000,000Announced Current
$50,000,000,000
Original Gross Area4,000,000 sq. ft.Announced
4,000,000 sq. ft.
Current Planned Gross AreaNearly 10 million sq. ft.Announced Current
Nearly 10 million sq. ft.
Planned It Capacity5 GWDesign Current
5 GW
Original Completion Forecast2030-12-31Forecast
2030-12-31
Jv Total Development Cost$27,000,000,000Contract Scope
$27,000,000,000
Blue Owl Jv Interest80 percentClosed Ownership
80 percent
Meta Jv Interest20 percentClosed Ownership
20 percent
Blue Owl Cash Contribution$7,000,000,000Closed Financing
$7,000,000,000
Meta Distribution$3,000,000,000Closed Financing
$3,000,000,000
Operational Jobs800 jobsForecast
800 jobs
Local Infrastructure Commitment$1,000,000,000Announced
$1,000,000,000