Record last updated Oct 28, 2026

Scope and capacity

Meta has operated its Forest City, North Carolina data center since 2012. The company reports more than $750 million invested, more than 275 operational jobs and continuing community programs associated with the campus.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Meta Forest City Data Center | Forest City | North Carolina | United States

Actual · Meta Forest City Data Center (Project)

Claim 55552 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Our Data Center Opens in Forest City, N.C.

    Meta · Document date: Apr 19, 2012 · Primary

    Source reference: SRC-3010 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/2012/04/facebook-data-center-opens-in-forest-city-n-c/

Lifecycle status · Operating

Actual · Meta Forest City Data Center (Project)

Claim 55553 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Our Data Center Opens in Forest City, N.C.

    Meta · Document date: Apr 19, 2012 · Primary

    Source reference: SRC-3010 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/2012/04/facebook-data-center-opens-in-forest-city-n-c/

Counterparties and capital

Meta Platforms, Inc. · Developer · CMP-0083