Skip to content
← Return to profile

Cartis diligence evidence schedule

Meta Clonee Data Center

PRJ-0644 · Site · Clonee, County Meath, Ireland

Record last updated Oct 28, 2026

Scope and capacity

Meta has operated and expanded its Clonee data center in County Meath since the project’s 2016 groundbreaking. The company reports approximately €1.4 billion invested and more than 300 operational jobs.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Meta Clonee Data Center | Clonee | County Meath | Ireland

Actual · Meta Clonee Data Center (Project)

Claim 55580 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Meta Data Center Locations

    Meta · Document date: Not stated · Primary

    Source reference: SRC-3017 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/all-locations/

Lifecycle status · Operating

Actual · Meta Clonee Data Center (Project)

Claim 55581 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Meta Data Center Locations

    Meta · Document date: Not stated · Primary

    Source reference: SRC-3017 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/all-locations/

Counterparties and capital

Meta Platforms, Inc. · Developer · CMP-0083

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.