Meta Altoona Data Center

PRJ-0632 · Site · Altoona, Iowa, United States

Record last updated Oct 28, 2026

Scope and capacity

Meta operates and continues to expand its Altoona data center campus in Iowa. The company reports more than $2.5 billion invested and more than 400 operational jobs, while municipal records document planning for additional buildings.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Meta Altoona Data Center | Altoona | Iowa | United States

Actual · Meta Altoona Data Center (Project)

Claim 55532 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Meta United States Data Center Locations

    Meta · Document date: Not stated · Primary

    Source reference: SRC-3004 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/us-locations/

Lifecycle status · Operating

Actual · Meta Altoona Data Center (Project)

Claim 55533 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Meta United States Data Center Locations

    Meta · Document date: Not stated · Primary

    Source reference: SRC-3004 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/us-locations/

Counterparties and capital

Meta Platforms, Inc. · Developer · CMP-0083