MEEZA M-Vault 6 Um Garn Campus

PRJ-0392 · Site · Um Garn, Qatar

Record last updated Oct 28, 2026

Scope and capacity

M-Vault 6 is MEEZA's 24 MW flagship campus under construction in Um Garn, with the first 6 MW targeted for use by the end of 2027. MEEZA M-Vault 6 Um Garn Campus is located in Um Garn, QA and is a data center campus in construction status.

Headline: 24 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Planned campus capacity · 24 MW

Planned / design or future potential · MEEZA M-Vault 6 Um Garn Campus (Project)

Claim 36637 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. MEEZA FY2025 Annual Report

    MEEZA · Document date: Feb 24, 2026 · Primary

    Source reference: SRC-2032 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/wp-content/uploads/Annual-Report-2025/

  2. MEEZA Q4 2025 earnings presentation

    MEEZA · Document date: Feb 24, 2026 · Corroborating

    Source reference: SRC-2033 · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/wp-content/uploads/2026/02/MZA-Earnings-Presentation-Q4-2025-24-Feb-2026-FINAL2.pdf

First tranche target · 2027

Actual · MEEZA M-Vault 6 Um Garn Campus (Project)

Claim 36639 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MEEZA FY2025 Annual Report

    MEEZA · Document date: Feb 24, 2026 · Primary

    Source reference: SRC-2032 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/wp-content/uploads/Annual-Report-2025/

Construction confirmed · True

Actual · MEEZA M-Vault 6 Um Garn Campus (Project)

Claim 36640 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MEEZA records 15% revenue growth during H1 2026

    MEEZA · Document date: Jul 28, 2026 · Corroborating

    Source reference: SRC-2031 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/meeza-records-15-revenue-growth-during-h1-2026/

  2. MEEZA FY2025 Annual Report

    MEEZA · Document date: Feb 24, 2026 · Primary

    Source reference: SRC-2032 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/wp-content/uploads/Annual-Report-2025/

Location · Um Garn

Actual · MEEZA M-Vault 6 Um Garn Campus (Project)

Claim 36641 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MEEZA FY2025 Annual Report

    MEEZA · Document date: Feb 24, 2026 · Primary

    Source reference: SRC-2032 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/wp-content/uploads/Annual-Report-2025/

First tranche utilization planned · True

Actual · MEEZA M-Vault 6 Um Garn Campus (Project)

Claim 36643 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MEEZA FY2025 Annual Report

    MEEZA · Document date: Feb 24, 2026 · Primary

    Source reference: SRC-2032 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.meeza.net/wp-content/uploads/Annual-Report-2025/

Counterparties and capital

MEEZA QSTP-LLC · Developer, Operator · CMP-0973