Cartis diligence evidence schedule

MC Digital Realty NRT Campus

PRJ-0491 · Site · Inzai, Chiba, Japan

Record last updated Oct 28, 2026

Scope and capacity

MC Digital Realty NRT Campus is an operating NRT campus containing NRT10, NRT12 and NRT14. Current sponsor guidance approaches 100 MW; the older 104 MW maximum is a dated design reference.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project identity · MC Digital Realty NRT Campus

Source report · MC Digital Realty NRT Campus (Project)

Claim 132349 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Digital Realty Opens NRT14 Data Center, Third Facility on NRT Campus

    Digital Realty · Document date: Apr 7, 2026 · Primary

    Source reference: SRC-6951 · Company announcement · Recorded authority: Party primary

    Source URL

    https://investor.digitalrealty.com/news-releases/news-release-details/digital-realty-opens-nrt14-data-center-third-facility-nrt-campus

  2. Construction Begins on NRT14

    MC Digital Realty · Document date: Apr 17, 2024 · Primary

    Source reference: SRC-6952 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.mc-digitalrealty.com/3782539

Counterparties and capital

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.