Scope and capacity

Microsoft is building a data center in La Porte, Indiana. As of July 2026, Ryan Central was grading and preparing the northern portion of the site for vertical construction; the project is not yet operational, and the earlier 538 MW figure remains an external planning estimate.

Headline: 538 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · La Porte Data Center | La Porte | Indiana | US

Actual · La Porte Data Center (Project)

Claim 71962 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte Data Center public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4148 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/indiana/

Lifecycle status · Preconstruction

Actual · La Porte Data Center (Project)

Claim 71963 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte Data Center public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4148 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/indiana/

Reported capacity · 538 MW

Planned / design or future potential · La Porte Data Center (Project)

Claim 71964 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. La Porte Data Center public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4148 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/indiana/

Capacity basis · 538 MW future full build site capacity; not measured operating IT load.

Actual · La Porte Data Center (Project)

Claim 71965 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte Data Center public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4148 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/indiana/

Construction status · Site grading and preparation

Actual · La Porte Data Center (Project)

Claim 77933 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte data center construction updates

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-4468 · Company announcement · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/la-porte-public-meeting-recap/

General contractor · Ryan Central

Actual · La Porte Data Center (Project)

Claim 77934 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte data center construction updates

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-4468 · Company announcement · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/la-porte-public-meeting-recap/

Vertical construction status · Not yet started as of July 2026

Actual · La Porte Data Center (Project)

Claim 77935 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte data center construction updates

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-4468 · Company announcement · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/la-porte-public-meeting-recap/

Capacity status · 538 MW remains an external planning estimate

Actual · La Porte Data Center (Project)

Claim 77936 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. La Porte Data Center public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4148 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/indiana/

Counterparties and capital

Microsoft · Developer · CMP-0017