Record last updated Oct 28, 2026

Scope and capacity

Khazna has acquired 225,000 square metres in Dammam for an AI-ready campus designed for up to 200 MW. No construction start, customer, utility allocation or opening date is public.

Headline: Up to 200 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Land acquired · True

Source report · Khazna Dammam AI-Ready Campus (Project)

Claim 42709 · Recorded claim type: Not stated · Review: Approved · Claim date: Dec 9, 2025

  1. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

  2. Khazna acquires land in Saudi Arabia for 200 MW AI-ready data centre

    Reuters / Zawya · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2392 · News report

    Source URL

    https://www.tradingview.com/news/reuters.com%2C2025-12-09%3Anewsml_Zaw4fVDjp%3A0-projects-uae-s-khazna-acquires-land-in-saudi-arabia-for-200mw-ai-ready-data-centre/

Site area · 225,000 square metres

Source report · Khazna Dammam AI-Ready Campus (Project)

Claim 42710 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Khazna enters Saudi Arabia, buys land in Dammam for 200 MW campus

    Data Center Dynamics · Document date: Dec 16, 2025 · Primary

    Source reference: SRC-2391

    Source URL

    https://www.datacenterdynamics.com/en/news/khazna-enters-saudi-arabia-buys-land-in-dammam-for-200mw-data-center-campus/

  2. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

Full campus design capacity · 200 MW up to

Planned / design or future potential · Khazna Dammam AI-Ready Campus (Project)

Claim 42711 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Khazna enters Saudi Arabia, buys land in Dammam for 200 MW campus

    Data Center Dynamics · Document date: Dec 16, 2025 · Primary

    Source reference: SRC-2391

    Source URL

    https://www.datacenterdynamics.com/en/news/khazna-enters-saudi-arabia-buys-land-in-dammam-for-200mw-data-center-campus/

  2. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

First saudi site · True

Source report · Khazna Dammam AI-Ready Campus (Project)

Claim 42712 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

Location precision · Dammam city only

Actual · Khazna Dammam AI-Ready Campus (Project)

Claim 42713 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Khazna enters Saudi Arabia, buys land in Dammam for 200 MW campus

    Data Center Dynamics · Document date: Dec 16, 2025 · Primary

    Source reference: SRC-2391

    Source URL

    https://www.datacenterdynamics.com/en/news/khazna-enters-saudi-arabia-buys-land-in-dammam-for-200mw-data-center-campus/

  2. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

Status · Preconstruction

Actual · Khazna Dammam AI-Ready Campus (Project)

Claim 42714 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Khazna enters Saudi Arabia, buys land in Dammam for 200 MW campus

    Data Center Dynamics · Document date: Dec 16, 2025 · Primary

    Source reference: SRC-2391

    Source URL

    https://www.datacenterdynamics.com/en/news/khazna-enters-saudi-arabia-buys-land-in-dammam-for-200mw-data-center-campus/

  2. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

Capacity boundary decision · Up to 200 MW future AI-ready design on acquired land; zero operating or allocated MW claimed

Actual · Khazna Dammam AI-Ready Campus (Project)

Claim 42733 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Khazna enters Saudi Arabia, buys land in Dammam for 200 MW campus

    Data Center Dynamics · Document date: Dec 16, 2025 · Primary

    Source reference: SRC-2391

    Source URL

    https://www.datacenterdynamics.com/en/news/khazna-enters-saudi-arabia-buys-land-in-dammam-for-200mw-data-center-campus/

  2. Khazna names new country head and advances Saudi expansion

    Khazna Data Centers · Document date: Dec 9, 2025 · Primary

    Source reference: SRC-2390 · Company announcement · Recorded authority: Party primary

    Source URL

    https://khaznadatacenters.com/press-release/khazna-data-centers-names-new-country-head-and-advances-expansion-plans-in-saudi-arabia-in-support-of-vision-2030/

Counterparties and capital

Khazna Data Centers · Operator · CMP-0137

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.