Cartis diligence evidence schedule
Kairos Hermes 2 Demonstration Plant
PRJ-0250 · Site · Oak Ridge, Tennessee, United States
Record last updated Oct 28, 2026
Scope and capacity
On September 21, 2026, Kairos Power announced a binding term sheet with Samsung C&T for up to $100 million in direct investment and in-kind engineering support, subject to approvals, and integrated engineering, procurement and construction collaboration for Hermes 2. The announcement is not evidence that the full amount has closed or been paid in cash; it is the same transaction cross-referenced by the Oak Ridge parent campus. First Google-linked power-producing Kairos deployment, now described as one 50-MWe reactor targeting 2030 operation. Kairos Hermes 2 Demonstration Plant is in Oak Ridge, TN, US and is a generation site with under construction status.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Current output · 50 MWe
Source report · Kairos Hermes 2 Demonstration Plant (Project)
Claim 23741 · Recorded claim type: Not stated · Review: Approved · Claim date: Aug 18, 2025
- Our first advanced nuclear reactor project with Kairos Power and TVA
Google · Document date: Aug 18, 2025 · Primary
Source reference: SRC-1327
Source URL
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
- Google, Kairos Power, TVA collaborate to meet America's growing energy needs
Kairos Power · Document date: Aug 18, 2025 · Corroborating
Source reference: SRC-1328
Source URL
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
- Kairos Power iterative development
Kairos Power · Document date: Not stated · Corroborating
Source reference: SRC-1331 · Company announcement
Source URL
https://www.kairospower.com/iterative-development
https://www.kairospower.com/iterative-development
Current unit count · 1 reactor
Design · Kairos Hermes 2 Demonstration Plant (Project)
Claim 23742 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Clean Electricity for the Tennessee Valley
Kairos Power · Document date: Oct 21, 2025 · Corroborating
Source reference: SRC-1329
Source URL
https://www.kairospower.com/updates/clean-electricity-for-the-tennessee-valley
https://www.kairospower.com/updates/clean-electricity-for-the-tennessee-valley
- Google, Kairos Power, TVA collaborate to meet America's growing energy needs
Kairos Power · Document date: Aug 18, 2025 · Primary
Source reference: SRC-1328
Source URL
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
- Kairos Power iterative development
Kairos Power · Document date: Not stated · Corroborating
Source reference: SRC-1331 · Company announcement
Source URL
https://www.kairospower.com/iterative-development
https://www.kairospower.com/iterative-development
Operations target · 2030
Forecast · Kairos Hermes 2 Demonstration Plant (Project)
Claim 23743 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Our first advanced nuclear reactor project with Kairos Power and TVA
Google · Document date: Aug 18, 2025 · Primary
Source reference: SRC-1327
Source URL
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
- Google, Kairos Power, TVA collaborate to meet America's growing energy needs
Kairos Power · Document date: Aug 18, 2025 · Corroborating
Source reference: SRC-1328
Source URL
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
PPA status · Binding PPA between Kairos Power and TVA
Source report · Kairos Hermes 2 Demonstration Plant (Project)
Claim 23744 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- The Time is Now
Kairos Power · Document date: May 28, 2026 · Corroborating
Source reference: SRC-1330
Source URL
https://www.kairospower.com/updates/the-time-is-now
https://www.kairospower.com/updates/the-time-is-now
- Our first advanced nuclear reactor project with Kairos Power and TVA
Google · Document date: Aug 18, 2025 · Primary
Source reference: SRC-1327
Source URL
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
- Google, Kairos Power, TVA collaborate to meet America's growing energy needs
Kairos Power · Document date: Aug 18, 2025 · Corroborating
Source reference: SRC-1328
Source URL
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
Groundbreaking date · 2026-04-17
Actual · Kairos Hermes 2 Demonstration Plant (Project)
Claim 23746 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- The Time is Now
Kairos Power · Document date: May 28, 2026 · Primary
Source reference: SRC-1330
Source URL
https://www.kairospower.com/updates/the-time-is-now
https://www.kairospower.com/updates/the-time-is-now
- One Year After Executive Orders, U.S. Nuclear Energy Renaissance
U.S. Department of Energy · Document date: May 23, 2026 · Corroborating
Source reference: SRC-1334
Source URL
https://www.energy.gov/ne/articles/one-year-after-executive-orders-us-nuclear-energy-renaissance-full-swing
https://www.energy.gov/ne/articles/one-year-after-executive-orders-us-nuclear-energy-renaissance-full-swing
Grid delivery structure · TVA grid injection with Google clean energy attributes
Source report · Kairos Hermes 2 Demonstration Plant (Project)
Claim 23747 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Our first advanced nuclear reactor project with Kairos Power and TVA
Google · Document date: Aug 18, 2025 · Primary
Source reference: SRC-1327
Source URL
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/
- Google, Kairos Power, TVA collaborate to meet America's growing energy needs
Kairos Power · Document date: Aug 18, 2025 · Corroborating
Source reference: SRC-1328
Source URL
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
https://www.kairospower.com/updates/google-kairos-power-tva-collaborate-to-meet-americas-growing-energy-needs
Counterparties and capital
Google · Customer · CMP-0112
Kairos Power LLC · Developer · CMP-0673
Tennessee Valley Authority · Utility provider · CMP-0674
U.S. Nuclear Regulatory Commission · Government authority · CMP-0421
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.