Iron Mountain NJE-1 New Jersey Data Center

Edison, New Jersey, United StatesOperating
Evidence
Planned critical IT
30 MW
Updated
Oct 28, 2026

NJE-1 is the operating Edison campus with 20.8 MW of current leaseable capacity, while Iron Mountain markets a 30 MW facility-power boundary. A separate 4 MW expansion is under construction and fully pre-leased. Cartis publishes the current leaseable figure and preserves the design and construction values as separate assertions. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Capacity

Reported capacity

Design

30 MW

Source

Reported capacity

Design

20.8 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

NJE-1 is the operating Edison campus with 20.8 MW of current leaseable capacity, while Iron Mountain markets a 30 MW facility-power boundary. A separate 4 MW expansion is under construction and fully pre-leased. Cartis publishes the current leaseable figure and preserves the design and construction values as separate assertions. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Milestones (1)
Project-specific evidence refreshed and reconciled

Aug 29, 2026 · Recorded actual event

Completed · Status changed

Source not linked

Participants

Iron Mountain Data Centers

Developer

Sources by role
Developer (1)

Capital & incentives

Financing records

Investment commitment

$59,500,000

Jun 30, 2026

SEC-reported expected investment for the 4 MW NJE-1 expansion; not a facility valuation.

Parties & sources

Iron Mountain Data Centers (Borrower)

Site & development

Location context

Actual

NJE-1 | Edison | NJ | US

Source

Location context

Actual

NJE-1 | Edison | NJ | US

Source

Project location

Actual

Edison, NJ, US

Source

Technical specifications

Renewable energy matching

Actual

Operator states 100% matched renewable energy where applicable

Source

Additional project facts

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

Iron Mountain publishes 30 MW for the NJE-1 facility record boundary.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

20.8 MW is Q2 2026 leaseable operating capacity. Iron Mountain markets a 30 MW facility power boundary and reports a separate 4 MW expansion under construction; neither is substituted for current leaseable IT.

Source

Operator or developer

Actual

Iron Mountain Data Centers

Source

Current lifecycle

Actual

Operating or in phased operation

Source

Capacity classification

Actual

It load

Source

Capacity basis

Actual

20.8 MW is Q2 2026 leaseable operating capacity. Iron Mountain markets a 30 MW facility power boundary and reports a separate 4 MW expansion under construction; neither is substituted for current leaseable IT.

Source

Customer utilization

Actual

Not publicly disclosed

Source

Source refresh date

Actual

2026-08-29

Source

Sec capacity comparison

Actual

Q2 2026 leaseable and development schedules reviewed

Source

Infrastructure & permits

Technical details (3)
Electric grid

Operational

20.8 MW

20.8 MW is Q2 2026 leaseable operating capacity. Iron Mountain markets a 30 MW facility-power boundary and reports a separate 4 MW expansion under construction; neither is substituted for current leaseable IT.

Fiber

Operational

Concurrently maintainable facility with 2N redundancy, 20+ carriers, modular deployment options and renewable-energy matching.

Cooling system

Operational

Cooling and resilience architecture is described at facility or campus level; instantaneous draw and tenant utilization remain undisclosed.

Public-source research. Plans may change. See Evidence for sources and qualifications.