Iron Mountain Navi Mumbai Campus

Navi Mumbai / Rabale, Maharashtra, IndiaPartially operational
Evidence
Planned critical IT
90 MW
Updated
Oct 28, 2026

Iron Mountain Navi Mumbai Campus links MUM-1, MUM-2 and MUM-3; 90-plus MW is a future aggregate, future aggregate capacity.

Constituent sites / phases

Capacity

Current operating capacity mum1 mum2

Actual

8.3 MW

Not included in reviewed operating IT capacity

Source

Future campus IT load minimum

Planned / design or future potential

90 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (1)
Web Werks brand integrated into Iron Mountain

Apr 1, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked

Participants

Iron Mountain Data Centers

Operator

Sources by role
Operator (1)
Operator (1)
Web Werks

Operator

Sources by role
Operator (1)
Operator (1)

Site & development

Campus area

Source report

5.5 acres

Source

Additional project facts

Identified facility count

Source report

3 facilities

Source

Operating facility count

Source report

2 facilities

Source

Future total is current live load

Source report

False

Source

Iron mountain ownership percent

Source report

100 %

Source

Web werks brand transition effective

Actual

2025-04-01

Source

Campus tenant disclosed

Source report

False

Source

Utility provider disclosed

Source report

False

Source

Infrastructure & permits

Technical details (1)
Electric grid

Partially operational

Current public sources

Public-source research. Plans may change. See Evidence for sources and qualifications.