Cartis diligence evidence schedule

Iron Mountain FRA-1 Frankfurt Data Center

PRJ-0953 · Site · Frankfurt, Hesse, Germany

Record last updated Oct 28, 2026

Scope and capacity

FRA-1 is a 27 MW wholesale facility in Frankfurt and is now reported in Iron Mountain’s operating portfolio at 100% leased. Cartis corrects the construction label to operating and keeps the 27 MW facility boundary separate from the combined 38 MW Frankfurt portfolio. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Headline: 27 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (17)

Location context · FRA-1 | Frankfurt | Hesse | DE

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 65734 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Lifecycle status · Construction

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 65735 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Reported capacity · 27 MW

Design · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 65736 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Capacity basis · Iron Mountain publishes 27 MW for the FRA-1 facility record boundary.

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 65737 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Location context · FRA-1 | Frankfurt | Hesse | DE

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89148 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Lifecycle status · Operating

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89149 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Reported capacity · 27 MW

Design · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89150 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Capacity basis · 27 MW is reported in Q2 2026 as operating and fully leased; the facility is no longer treated as construction stage.

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89151 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Operator or developer · Iron Mountain Data Centers

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89152 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Project location · Frankfurt, Hesse, DE

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89153 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Current lifecycle · Under development

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89154 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Capacity classification · It load

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89155 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Capacity basis · 27 MW is reported in Q2 2026 as operating and fully leased; the facility is no longer treated as construction stage.

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89156 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Customer utilization · Not publicly disclosed

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89158 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Source refresh date · 2026-08-29

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89160 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain FRA-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3715 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/emea/frankfurt

Renewable energy matching · Operator states 100% matched renewable energy where applicable

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89161 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain Frankfurt campus current profile

    Iron Mountain Data Centers · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-4960 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://digitalresourcecenter.ironmountain.com/data-centers/locations/emea/frankfurt

Sec capacity comparison · Q2 2026 leaseable and development schedules reviewed

Actual · Iron Mountain FRA-1 Frankfurt Data Center (Project)

Claim 89162 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain Q2 2026 supplemental financial information

    Iron Mountain Incorporated / U.S. SEC · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-4961 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1020569/000102056926000068/q22026srpfinal.htm

Counterparties and capital

Iron Mountain Data Centers · Developer · CMP-1123

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.