Iron Mountain DEN-1 Denver Data Center

Denver, Colorado, United StatesOperating / Stabilized
Capacity
14.4 MW
Planned critical IT
Lead participant
Iron Mountain Data Centers
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Iron Mountain DEN-1 Denver Data Center

Iron Mountain DEN-1 Denver Data Center, also known as Iron Mountain DEN-1, is a data center project in Denver, CO, US. Purpose-built 180,000-square-foot Denver facility with 14.4 MW of total power capacity on a six-acre campus. Tier III-design facility with diverse utility feeds, N+1 redundancy, carrier neutrality and renewable-energy matching. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load14.4 MWDesign · Iron Mountain DEN-1 Denver Data Center
It Load11.3 MWDesign · Iron Mountain DEN-1 Denver Data Center

Development

1 phases · 1 milestones
Operating facility and documented expansionOperational

Iron Mountain DEN-1 Denver Data Center, also known as Iron Mountain DEN-1, is a data center project in Denver, CO, US. Purpose-built 180,000-square-foot Denver facility with 14.4 MW of total power capacity on a six-acre campus. Tier III-design facility with diverse utility feeds, N+1 redundancy, carrier neutrality and renewable-energy matching. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Aug 29, 2026
Project-specific evidence refreshed and reconciled
Completed

Infrastructure

Electric GridOperational

11.3 MW

11.3 MW is the Q2 2026 SEC-reported leaseable operating capacity. The larger marketed facility-power or design boundary is retained as a separate assertion and is not presented as current operating IT.

FiberOperational

Tier III-design facility with diverse utility feeds, N+1 redundancy, carrier neutrality and renewable-energy matching.

Cooling SystemOperational

Cooling and resilience architecture is described at facility or campus level; instantaneous draw and tenant utilization remain undisclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

17 facts
Location Context
DEN-1 | Denver | CO | US
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
14.4 MW
Design
Capacity Basis
Iron Mountain publishes 14.4 MW for the DEN-1 facility record boundary.
Actual
Location Context
DEN-1 | Denver | CO | US
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
11.3 MW
Design
Capacity Basis
11.3 MW is the Q2 2026 SEC-reported leaseable operating capacity. The larger marketed facility power or design boundary is retained as a separate assertion and is not presented as current operating IT.
Actual
Operator Or Developer
Iron Mountain Data Centers
Actual
Project Location
Denver, CO, US
Actual
Current Lifecycle
Operating or in phased operation
Actual
Capacity Classification
It load
Actual
Capacity Basis
11.3 MW is the Q2 2026 SEC-reported leaseable operating capacity. The larger marketed facility power or design boundary is retained as a separate assertion and is not presented as current operating IT.
Actual
Customer Utilization
Not publicly disclosed
Actual
Source Refresh Date
2026-08-29
Actual
Renewable Energy Matching
Operator states 100% matched renewable energy where applicable
Actual
Sec Capacity Comparison
Q2 2026 leaseable and development schedules reviewed