Cartis diligence evidence schedule

Iron Mountain CHI-1 Chicago Data Center

PRJ-0950 · Site · Des Plaines, Illinois, United States

Record last updated Oct 28, 2026

Scope and capacity

CHI-1 is an operating Des Plaines facility with 12 MW of current leaseable capacity. Iron Mountain markets a 36 MW facility boundary, and the SEC reports a further 24 MW fully pre-leased but not yet in construction. The available sources support the documented development context. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Headline: 36 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (17)

Location context · CHI-1 | Des Plaines | IL | US

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 65722 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Lifecycle status · Operating

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 65723 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Reported capacity · 36 MW

Design · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 65724 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Capacity basis · Iron Mountain publishes 36 MW for the CHI-1 facility record boundary.

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 65725 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Location context · CHI-1 | Des Plaines | IL | US

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89098 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Lifecycle status · Operating

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89099 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Reported capacity · 12 MW

Design · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89100 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Capacity basis · 12 MW is Q2 2026 leaseable operating capacity. The 36 MW marketed facility boundary includes a 24 MW future phase that was fully pre leased but not reported as construction started.

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89101 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Operator or developer · Iron Mountain Data Centers

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89102 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Project location · Des Plaines, IL, US

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89103 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Current lifecycle · Operating or in phased operation

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89104 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Capacity classification · It load

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89105 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Capacity basis · 12 MW is Q2 2026 leaseable operating capacity. The 36 MW marketed facility boundary includes a 24 MW future phase that was fully pre leased but not reported as construction started.

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89106 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Customer utilization · Not publicly disclosed

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89108 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Source refresh date · 2026-08-29

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89110 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain CHI-1 facility profile

    Iron Mountain Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3711 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations/na/chicago-data-center

Renewable energy matching · Operator states 100% matched renewable energy where applicable

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89111 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain global data-center locations

    Iron Mountain Data Centers · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-4953 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.ironmountain.com/data-centers/locations

Sec capacity comparison · Q2 2026 leaseable and development schedules reviewed

Actual · Iron Mountain CHI-1 Chicago Data Center (Project)

Claim 89112 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Iron Mountain Q2 2026 supplemental financial information

    Iron Mountain Incorporated / U.S. SEC · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-4954 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1020569/000102056926000068/q22026srpfinal.htm

Counterparties and capital

Iron Mountain Data Centers · Developer · CMP-1123

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.