IREN Bundey AI Data Center Campus
- Planned critical IT
- 600 MW
- Updated
- Oct 28, 2026
IREN is planning a large data center campus near Bundey in South Australia. The federal environmental referral describes three data halls of up to 200 MW of IT capacity each within an 800 MW site connection and a six-to-eight-year staged build. IREN is associated with the development in Bundey, Mid Murray Council area, South Australia, AU. The disclosed development scope includes 600 MW planned IT load across three halls; 800 MW site connection envelope; federal environmental referral under review; energization planned from 2028. Power and physical infrastructure include four 330 kV feeder exits, a bulk substation, three primary substations and overhead transmission connections are planned. The federal referral describes three planned data halls of up to 200 MW of IT capacity each.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Project-wide phase for IREN Bundey AI Data Center Campus; capacity class is it load.
Milestones (2)
Aug 13, 2026 · Recorded actual event
Completed · Announced
Source not linkedDate not disclosed · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- IREN announces first Australian data center campus · Aug 13, 2026 · Primary
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (2)
Planned or represented
600 MW
The federal referral describes three planned data halls of up to 200 MW of IT capacity each.
Planned or represented
Four 330 kV feeder exits, a bulk substation, three primary substations and overhead transmission connections are planned.
Project map
Other · Under review
IREN Bundey AI Data Center Campus
Australian Department of Climate Change, Energy, the Environment and Water
Aug 1, 2026
Sources (2)
- IREN announces first Australian data center campus · Aug 13, 2026 · Primary
- Bundey federal environmental referral · Aug 1, 2026 · Corroborating
Public-source research. Plans may change. See Evidence for sources and qualifications.