Data center siteSite record

Hyperscale Data Center Bełchatów

Domiechowice, Gmina Bełchatów, PolandPreconstruction
Capacity
500 MW
Utility capacity
Lead participant
Gmina Bełchatów
Government Authority
Last updated
Aug 26, 2026
Most recent public record update

About Hyperscale Data Center Bełchatów

Public authorities describe a roughly 50-hectare hyperscale campus concept in Domiechowice with connection conditions for up to 500 MW. Environmental and spatial-planning work continues, and the first object is targeted around 2029.

Capacity

Utility capacity
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Utility Service500 MWForecast · Hyperscale Data Center Bełchatów

Development

3 phases · 3 milestones
Domiechowice planning and connection phaseAnnounced Or Preconstruction

The unnamed investor holds preliminary land agreements; title transfer and permits remain conditional.

First objectPlanned

Target from municipal-source reporting; no detailed building program disclosed.

1 building

Possible combined second zonePlanned

Only if two industrial zones are combined; excluded from canonical 500 MW headline.

Feb 12, 2026
Łódź authorities discuss Domiechowice project
Completed
Apr 2, 2026
Mayor reports connection decision and ongoing plans
Completed
Jan 1, 2029
First Bełchatów facility target
Forecast

Infrastructure

Utility ServicePlanned Or Represented

500 MW

Connection conditions reported as obtained; delivery schedule and final agreement remain unresolved.

Utility ServicePotential Or Planned

PSE and PGE Dystrybucja discussions are underway; no energized supply is inferred.

Electric GridPotential Or Planned

1,000 MW

Approximately 1 GW only if two 500 MW industrial zones are combined.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
2

No map point available

Power & interconnection: 3

Facts & sources

Published claims and their source links.

10 facts
Current Status
Predevelopment planning and environmental review
Actual
Site Area
Approximately 50 hectares
Forecast
Connection Capacity
500 MW
Forecast
Connection Conditions Status
Obtained for 500 MW
Actual
Environmental Decision Status
In process
Permitted
Spatial Plan Status
General and local plans in preparation
Actual
Road Access Plan
4 roundabouts
Forecast
First Object Target
Around 2029
Forecast
Investor Identity
Not publicly identified
Proposal
Land Control
Preliminary agreements signed; title transfer conditional
Actual