Cartis diligence evidence schedule

High Performance Compute Data Center Campus

PRJ-1078 · Site · Millard, Utah, United States

Record last updated Oct 28, 2026

Scope and capacity

Joule Capital Partners is developing a high-performance-compute campus in Millard County, Utah, with Caterpillar and Wheeler Machinery supporting a planned 4 GW onsite generation system. The concept combines distributed generation, heat recovery and direct-liquid cooling for a phased AI-compute buildout. The 4 GW figure describes the energy package and is not evidence of operating IT load. Tenant commitments, generation permits, water requirements, financing and the construction schedule remain prospective.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · High Performance Compute Data Center Campus | Millard | Utah | US

Actual · High Performance Compute Data Center Campus (Project)

Claim 70284 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Lifecycle status · Preconstruction

Actual · High Performance Compute Data Center Campus (Project)

Claim 70285 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Capacity basis · 4,000 MW onsite generation; not measured operating IT load. Four gigawatt onsite generation package; not operating IT load.

Actual · High Performance Compute Data Center Campus (Project)

Claim 70287 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Location context · High Performance Compute Data Center Campus | Millard | Utah | US

Actual · High Performance Compute Data Center Campus (Project)

Claim 74442 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Lifecycle status · Preconstruction

Actual · High Performance Compute Data Center Campus (Project)

Claim 74443 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Generation partner · Caterpillar

Actual · High Performance Compute Data Center Campus (Project)

Claim 74446 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Equipment partner · Wheeler Machinery

Actual · High Performance Compute Data Center Campus (Project)

Claim 74447 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Cooling system · Direct liquid cooling and heat recovery

Actual · High Performance Compute Data Center Campus (Project)

Claim 74448 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High Performance Compute Data Center Campus project source

    Caterpillar · Document date: Aug 7, 2025 · Primary

    Source reference: SRC-4000 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.caterpillar.com/en/news/corporate-press-releases/h/joule-caterpillar-wheeler.html

Counterparties and capital

Joule Capital Partners · Developer · CMP-1496

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.