Cartis diligence evidence schedule

Haven Oak Technology Park

PRJ-1142 · Site · Dinwiddie County, Virginia, United States

Record last updated Oct 28, 2026

Scope and capacity

Dinwiddie County records an August 31, 2026 revised Haven Oak submission removing development from the Core Battlefield Area on the West Bay, restricting cooling to air-cooled/closed-loop non-evaporative systems, and increasing buffers. These are proposed design revisions, not approved entitlements. Tract has applied to rezone roughly 986.9 acres in Dinwiddie County, Virginia for Haven Oak Technology Park. The proposal seeks an Emerging Technologies District designation and conditional-use authorization for a data-center campus; county officials state no decision has been made, and no firm MW total has been officially disclosed.

Headline: 900 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Haven Oak Technology Park | Dinwiddie County | Virginia | US

Actual · Haven Oak Technology Park (Project)

Claim 71890 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Lifecycle status · Proposed

Actual · Haven Oak Technology Park (Project)

Claim 71891 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Reported capacity · 900 MW

Planned / design or future potential · Haven Oak Technology Park (Project)

Claim 71892 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Capacity basis · 900 MW future full build site capacity; not measured operating IT load.

Actual · Haven Oak Technology Park (Project)

Claim 71893 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Site area · 986.9 acres

Actual · Haven Oak Technology Park (Project)

Claim 77790 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Application type · Rezoning plus conditional use permit

Actual · Haven Oak Technology Park (Project)

Claim 77791 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Decision status · No decision made

Actual · Haven Oak Technology Park (Project)

Claim 77792 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak joint statement

    Dinwiddie County · Document date: Jul 14, 2026 · Primary

    Source reference: SRC-4430 · Government record · Recorded authority: Official primary

    Source URL

    https://dinwiddieva.us/m/newsflash/home/detail/878

Capacity status · 900 MW remains a secondary estimate; not officially disclosed

Actual · Haven Oak Technology Park (Project)

Claim 77793 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haven Oak Technology Park project source

    Dinwiddie County · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4126 · Government record · Recorded authority: Official primary

    Source URL

    https://www.dinwiddieva.us/1413/Application-Documents-for-Haven-Oak-Tech

Counterparties and capital

Tract · Developer · CMP-1271

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.