Green Mountain FRA-Mainz / Green Rocks Campus
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
Green Mountain's current FRA-Mainz operator page, checked October 28, 2026, states that the entire 54 MW facility is contracted to one hyperscale client. This is a leasing statement, not confirmation of operating capacity; the earlier 36 MW agreement remains part of the project's history. Green Mountain and KMW are building a three-building data center campus on Ingelheimer Aue in Mainz. Current sponsor pages disagree between 54 MW and 80 MW, and the first section is targeted for Q4 2026.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
18 MW original phase; current RFS target Q4 2026.
1 building
Second section started; 18 MW and about 6,000 sqm IT space.
1 building
No verified construction start.
3 buildings
Capacity handover over roughly 3.5 years; phase allocation undisclosed.
Milestones (5)
Oct 30, 2023 · Recorded actual event
Completed · Construction started
Source not linkedFeb 7, 2025 · Recorded actual event
Completed · Status changed
Source not linkedSep 1, 2025 · Recorded actual event
Completed · Customer commitment
Source not linkedJan 21, 2026 · Recorded actual event
Completed · Construction started
Source not linkedJul 20, 2026 · Recorded actual event
Completed · Permit approved
Source not linkedParticipants
Other participants (1)
Site & development
Additional project facts
Infrastructure & permits
Technical details (7)
Under construction
54 MW
Green Mountain current figure and original approved plan.
Under construction
18 MW
Per-building IT figure for three-building plan.
Under construction
18,000 sqm
Three buildings of about 6,000 sqm each.
Planned or represented
60 MW thermal
Heat output, not IT load or electrical generation.
Permitted or installed
54 MW electrical
Twelve-engine H2-ready plant; also expected to serve grid hours.
Planned or represented
110 kV
Redundant supplies; renewable-energy portfolio claim.
Planned or represented
Rhine water cooling with heat-reuse priority.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.