Google opened its air-cooled Waltham Cross data center in 2025 after announcing a US$1 billion site investment. Google Waltham Cross Data Center is located in Waltham Cross / Cheshunt, ENG, GB and is a data center campus in operating status.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (10)
Campus site area · 33 acres
Actual · Google Waltham Cross Data Center (Project)
Claim 32892 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Our $1 billion investment in a new UK data centre
Google · Document date: Jan 18, 2024 · Primary
Source reference: SRC-1842 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/google-1-billion-investment-in-a-new-uk-data-centre/
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/google-1-billion-investment-in-a-new-uk-data-centre/
Site specific investment · $1 billion
Actual · Google Waltham Cross Data Center (Project)
Claim 32893 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Our $1 billion investment in a new UK data centre
Google · Document date: Jan 18, 2024 · Primary
Source reference: SRC-1842 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/google-1-billion-investment-in-a-new-uk-data-centre/
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/google-1-billion-investment-in-a-new-uk-data-centre/
Construction announced · True
Actual · Google Waltham Cross Data Center (Project)
Claim 32894 · Recorded claim type: Actual · Review: Approved · Claim date: Jan 18, 2024
- Google set to build new data centre in Cheshunt
Borough of Broxbourne · Document date: Jan 22, 2024 · Corroborating
Source reference: SRC-1843 · Government record · Recorded authority: Official primary
Source URL
https://www.broxbourne.gov.uk/news/article/321/google-set-to-build-new-data-centre-in-cheshunt
https://www.broxbourne.gov.uk/news/article/321/google-set-to-build-new-data-centre-in-cheshunt
- Our $1 billion investment in a new UK data centre
Google · Document date: Jan 18, 2024 · Primary
Source reference: SRC-1842 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/google-1-billion-investment-in-a-new-uk-data-centre/
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/google-1-billion-investment-in-a-new-uk-data-centre/
Opened · True
Actual · Google Waltham Cross Data Center (Project)
Claim 32895 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Our new Waltham Cross data center is part of our two-year £5 billion investment
Google · Document date: Sep 16, 2025 · Corroborating
Source reference: SRC-1844 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/
- US-UK pact will boost advances in drug discovery and create jobs
UK Government · Document date: Sep 16, 2025 · Corroborating
Source reference: SRC-1845 · Government record · Recorded authority: Official primary
Source URL
https://www.gov.uk/government/news/us-uk-pact-will-boost-advances-in-drug-discovery-create-tens-of-thousands-of-jobs-and-transform-lives
https://www.gov.uk/government/news/us-uk-pact-will-boost-advances-in-drug-discovery-create-tens-of-thousands-of-jobs-and-transform-lives
- Waltham Cross, United Kingdom
Google · Document date: Not stated · Primary
Source reference: SRC-1841 · Company announcement · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/waltham-cross/
https://datacenters.google/locations/waltham-cross/
Opening date · 2025-09-16
Actual · Google Waltham Cross Data Center (Project)
Claim 32896 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Our new Waltham Cross data center is part of our two-year £5 billion investment
Google · Document date: Sep 16, 2025 · Primary
Source reference: SRC-1844 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/
- US-UK pact will boost advances in drug discovery and create jobs
UK Government · Document date: Sep 16, 2025 · Corroborating
Source reference: SRC-1845 · Government record · Recorded authority: Official primary
Source URL
https://www.gov.uk/government/news/us-uk-pact-will-boost-advances-in-drug-discovery-create-tens-of-thousands-of-jobs-and-transform-lives
https://www.gov.uk/government/news/us-uk-pact-will-boost-advances-in-drug-discovery-create-tens-of-thousands-of-jobs-and-transform-lives
Construction supplier count greater than · 250 companies
Actual · Google Waltham Cross Data Center (Project)
Claim 32897 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Waltham Cross, United Kingdom
Google · Document date: Not stated · Primary
Source reference: SRC-1841 · Company announcement · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/waltham-cross/
https://datacenters.google/locations/waltham-cross/
Advanced air cooling · True
Actual · Google Waltham Cross Data Center (Project)
Claim 32898 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Waltham Cross, United Kingdom
Google · Document date: Not stated · Primary
Source reference: SRC-1841 · Company announcement · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/waltham-cross/
https://datacenters.google/locations/waltham-cross/
Water use limited to domestic use company claim · True
Actual · Google Waltham Cross Data Center (Project)
Claim 32899 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Waltham Cross, United Kingdom
Google · Document date: Not stated · Primary
Source reference: SRC-1841 · Company announcement · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/waltham-cross/
https://datacenters.google/locations/waltham-cross/
Offsite heat recovery ready · True
Actual · Google Waltham Cross Data Center (Project)
Claim 32900 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Waltham Cross, United Kingdom
Google · Document date: Not stated · Primary
Source reference: SRC-1841 · Company announcement · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/waltham-cross/
https://datacenters.google/locations/waltham-cross/
Broader uk investment program · £5 billion
Actual · Google Waltham Cross Data Center (Project)
Claim 32903 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Our new Waltham Cross data center is part of our two-year £5 billion investment
Google · Document date: Sep 16, 2025 · Primary
Source reference: SRC-1844 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/
https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/
Counterparties and capital
Borough of Broxbourne · Government authority · CMP-0892
Google · Developer, Operator, Owner · CMP-0112
$1,000,000,000 · Jan 18, 2024
Site-specific Waltham Cross investment announcement.
Google (Sponsor)
Sources (1)
- Our $1 billion investment in a new UK data centre · Jan 18, 2024
Financing record 95; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.