Hanau / Industriepark Wolfgang, Hesse, GermanyOperating
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026
Utility
EnBW · Evonik · Umicore

On November 11, 2025, Google announced an expansion of its Hanau site as part of a Germany-wide €5.5 billion investment programme through 2029. The announcement does not allocate that national investment total to Hanau or disclose a Hanau-specific expansion capacity or opening date. Google opened its Hanau data center in 2023 after a prior 2022 target. The four-story, 10,000-square-metre facility supports the Frankfurt cloud region; Google has not disclosed a site capacity.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Hanau build and handoverChanged or cancelled

1 building

Historical construction phase; actual opening occurred in 2023.

Hanau operating facilityOperational

1 building

Google-owned Cloud data center supporting the Frankfurt cloud region.

Waste-heat reuse studyPlanned

No delivered heat volume, commissioning date or binding offtake was located.

Milestones (4)
NDC-Garbe building handover described

Aug 31, 2021 · Recorded actual event

Completed · Construction completed

Source not linked
Earlier 2022 operating target

2022 · Forecast / planned record

Forecast · Forecast completion

Source not linked
Google opens Hanau data center

Oct 6, 2023 · Recorded actual event

Completed · Commercial operation

Source not linked
Parties examine waste-heat reuse

Oct 6, 2023 · Forecast / planned record

Forecast · Event type not stated

Source not linked

Participants

Google

Owner

Sources by role
Owner (1)
Owner (1)
NDC-Garbe

Developer

Sources by role
Developer (1)
Other participants (5)
EnBW

Utility provider

Sources by role
Utility provider (1)
Evonik

Utility provider

Sources by role
Utility provider (1)
Stadt Hanau

Government authority

Sources by role
Government authority (1)
Umicore

Utility provider

Sources by role
Utility provider (1)

Site & development

Building stories

Actual

4 stories

Hanau build and handover · Phase

Source

Building area

Actual

10,000 sqm

Hanau build and handover · Phase

Source

Technical specifications

Cooling design

Design

Air/free cooling with air cooled chillers

Source

Additional project facts

Operational status

Actual

Operating

Source

Opening year

Actual

2023

Source

Ownership distinction

Actual

First Google owned Cloud data center in Germany

Source

Actual opening

Actual

2023-10-06

Hanau operating facility · Phase

Source

Cloud region support

Actual

Frankfurt cloud region

Source

Waste heat reuse

Actual

Google, EnBW, Evonik and Umicore examining options

Waste-heat reuse study · Phase

Source

Infrastructure & permits

Technical details (3)
Cooling system

Operational

Air/free cooling and air-cooled chillers; no site water-use metric located.

Renewable energy supply

Reported context

140 MW portfolio

Germany-wide ENGIE wind/solar portfolio; not Hanau site capacity or utility service.

Heat reuse

Potential or planned

Google, EnBW, Evonik and Umicore were examining reuse options; no operating system asserted.