Google Hamina Data Center Campus
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
- Utility
- Haminan Energia
On September 14, 2026, the City of Hamina confirmed that Google and the city had signed additional land-purchase deeds for potential campus expansion. The land acquisition is not evidence that new buildings have been constructed or commissioned; Google's separate Finland-wide investment programme is not wholly allocated to Hamina. Google's single former-Summa-paper-mill campus, including successive building expansions and heat-recovery infrastructure. Google Hamina Data Center Campus is in Hamina, Kymenlaakso, FI and is a data center campus with operational status.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
First operational phase.
6 buildings
Sixth building was under construction in 2020; exact current count remains open.
No primary completion confirmation by cutoff.
Milestones (5)
2009 · Recorded actual event
Completed · Event type not stated
Source not linkedSep 2011 · Recorded actual event
Completed · Event type not stated
Source not linkedSep 21, 2020 · Recorded actual event
Completed · Event type not stated
Source not linkedMay 20, 2024 · Recorded actual event
Completed · Announced
Source not linkedJun 2, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Our first offsite heat recovery project lands in Finland · May 20, 2024 · Corroborating
Developer (1)
- Google Hamina data center · Primary
Other participants (2)
Government authority
Sources by role
Government authority (1)
- Google Hamina data center · Primary
Utility provider
Sources by role
Utility provider (1)
- Blue, yellow and green: Google invests in Sweden · Jun 2, 2026 · Corroborating
Utility provider (1)
- Our first offsite heat recovery project lands in Finland · May 20, 2024 · Primary
Capital & incentives
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (3)
Operational
Cooling system uses seawater from the Gulf of Finland; volume not established.
Operational
External district-heat delivery launched; expected to cover roughly 80% of demand.
Secured or contracted
190 MW
Three Finland PPAs totaling 190 MW; supply measure, not campus load.
Project map
Permit · Status not stated
Hamina campus
City of Hamina
Sources (2)
- Our first offsite heat recovery project lands in Finland · May 20, 2024 · Corroborating
- Google Hamina data center · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.