Google Dorchester County Data Center Program

Ridgeville / St. George, South Carolina, United StatesPartially operational
Capacity
See sites
2 constituent sites
Lead participant
Google
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Google Dorchester County Data Center Program

Google Dorchester County Data Center Program comprises distinct physical campuses. Google Dorchester County Data Center Program is located in Ridgeville / St. George, SC, US and is a development program in partially operational status. Participants include Google as developer. Key milestones include Two Dorchester campuses and USD2bn combined investment announced (2024-09-26) and USD9bn statewide 2026-2027 investment announced (2025-10-13). renewable energy credits — 600 MW+: South Carolina solar and solar-plus-storage REC portfolio; not assigned to either campus and not IT capacity. Capital records include announced sponsor capital program of 2 USD billion for Combined Dorchester investment for both campuses; no site split.

Constituent sites

2 linked

Projects sharing a market, utility, or organization.

1 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

0 phases · 3 milestones
Jan 1, 2024
Google reports opening a Dorchester data center without identifying the campus
Completed
Sep 26, 2024
Two Dorchester campuses and USD2bn combined investment announced
Completed
Oct 13, 2025
USD9bn statewide 2026-2027 investment announced
Completed

Infrastructure

Renewable Energy SupplySecured Or Contracted

600 MW+

South Carolina solar and solar-plus-storage REC portfolio; not assigned to either campus and not IT capacity.

Constituent-site map

0 of 2 constituent sites mapped
Child-site facts
0
Mapped child sites
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

14 facts
Physical Campus Count
2 campuses
Reported Rounded
Dorchester Combined Investment
$2 billion
Reported Rounded
Dorchester Combined Operational Jobs
200 jobs
Reported Rounded
Long Term Construction Jobs
1,200 jobs
Reported Rounded
Active Construction Confirmed
2025-10-13
Actual
Statewide 2026 2027 Investment
$9 billion
Reported Rounded
Statewide Envelope Allocable To Program
False
Actual
Unidentified Dorchester Opening Year
2024
Reported Rounded
Site Of Reported Opening Identified
False
Actual
Program Status
Partially operational and under construction
Actual
Statewide Facility Count
3 facilities
Reported Rounded
Dorchester It Capacity Disclosed
False
Actual
Statewide Rec Portfolio
600 MW+
Reported Rounded
Rec Portfolio Is Campus Capacity
False
Actual