Skip to content
All records
Data center siteSite record

Google Council Bluffs Core Campus

Council Bluffs / 1430 Veterans Memorial Highway, Iowa, United StatesOperating / Stabilized
Capacity
No public figure
Lead participant
Google
Developer
Last updated
Aug 24, 2026
Most recent public record update

About Google Council Bluffs Core Campus

Google's original Council Bluffs campus began development in 2007 and remains part of the company's mature Iowa infrastructure footprint. Google Council Bluffs Core Campus is in Council Bluffs / 1430 Veterans Memorial Highway, IA, US and is a data center campus with operational status. Participants include Google LLC as developer. Development comprises Original campus development (operational). Key milestones include Early approximately 200,000-square-foot facility completed. (2009-12-31).

Program relationships

1 linked

Projects sharing a market, utility, or organization.

2 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

1 phases · 1 milestones
Original campus developmentOperational

Early approximately 200,000-square-foot facility; later building inventory requires permit review.

1 building

Dec 31, 2009
Early approximately 200,000-square-foot facility completed
Completed

Infrastructure

No public infrastructure records are attached.

Project map

0 of 1 project point mapped
Infrastructure facts
0
Mapped records
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

2 facts
Early Facility Floor Area
200,000 sq. ft.
Reported Rounded
Operating Status
Operating
Actual