Google Cerrillos Data Center

Cerrillos, RM, ChileStatus under review
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Separate two-building Santiago proposal. Original water-cooled regulatory path was withdrawn in 2024; Google promised a new air-cooled filing at the same site. Google Cerrillos Data Center is in Cerrillos, RM, CL and is a data center campus with predevelopment status.

Program relationships

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Original water-cooled projectChanged or cancelled

2 buildings

Original environmental design is no longer an executable project approval.

Promised air-cooled successor projectAnnounced or preconstruction

Same site; new primary filing not located by cutoff.

Milestones (5)
Original Cerrillos environmental declaration filed

Jul 15, 2019 · Recorded actual event

Completed · Event type not stated

Source not linked
Original project receives RCA 127/2020

2020 · Recorded actual event

Completed · Permit approved

Source not linked
Air-cooling modification submitted as pertinence query

Feb 16, 2022 · Recorded actual event

Completed · Status changed

Source not linked
Court partially annuls approval and suspends execution

Feb 26, 2024 · Recorded actual event

Completed · Event type not stated

Source not linked
Google withdraws original process and promises new air-cooled filing

Sep 17, 2024 · Recorded actual event

Completed · Status changed

Source not linked

Participants

Google

Developer

Sources by role
Developer (1)
Developer (1)
Other participants (3)
Municipalidad de Cerrillos

Government authority

Sources by role
Government authority (1)
Government authority (1)
Segundo Tribunal Ambiental

Government authority

Sources by role
Government authority (1)
Government authority (1)
Servicio de Evaluación Ambiental de Chile

Government authority

Sources by role
Government authority (1)
Government authority (1)

Site & development

Original data center buildings

Source report

2 buildings

Source

Technical specifications

Original cooling

Source report

Groundwater based cooling towers

Source

Additional project facts

Original approval

Source report

RCA 127/2020 partially annulled and suspended

Source

Permit process withdrawal

Actual

2024-09-17

Source

Infrastructure & permits

Technical details (3)
Electric grid

Cancelled or not proceeding

Original project included a substation and underground double-circuit line.

Cooling system

Cancelled or not proceeding

Original cooling towers and three groundwater wells; central climate/water issue.

Cooling system

Planned or represented

New filing promised; detailed current design not publicly disclosed.

Permit · Status not stated

R-271-2020 / R-270-2020 judicial review

Segundo Tribunal Ambiental

Feb 26, 2024

Sources (2)
Permit · Status not stated

Cerrillos RCA 127/2020

Servicio de Evaluación Ambiental de Chile

Sep 17, 2024

Sources (4)
Permit · Status not stated

Air-cooled successor environmental process

Servicio de Evaluación Ambiental de Chile

Sources (1)