Cartis diligence evidence schedule

Global Switch Paris North

PRJ-1006 · Site · Clichy, Île-de-France, France

Record last updated Oct 28, 2026

Scope and capacity

Global Switch Paris North is a separately named operating building within Global Switch’s Clichy campus. The 24 MW operator boundary is retained for this building; shared campus connectivity and more than 50,000 square metres of floor area are not reassigned as building-specific values. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Headline: 24 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (18)

Location context · Global Switch Paris North | Clichy | Île de-France | FR

Actual · Global Switch Paris North (Project)

Claim 67296 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Lifecycle status · Operating

Actual · Global Switch Paris North (Project)

Claim 67297 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Reported capacity · 24 MW

Design · Global Switch Paris North (Project)

Claim 67298 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Capacity basis · Global Switch publishes 24 MW for this project boundary.

Actual · Global Switch Paris North (Project)

Claim 67299 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Location context · Global Switch Paris North | Clichy | Île de-France | FR

Actual · Global Switch Paris North (Project)

Claim 84916 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Lifecycle status · Operating

Actual · Global Switch Paris North (Project)

Claim 84917 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Reported capacity · 24 MW

Design · Global Switch Paris North (Project)

Claim 84918 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Capacity basis · 24 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Global Switch Paris North (Project)

Claim 84919 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Operator confirmed · Global Switch

Actual · Global Switch Paris North (Project)

Claim 84920 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Project location · Clichy, Île de-France, FR

Actual · Global Switch Paris North (Project)

Claim 84921 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Current lifecycle · Operating

Actual · Global Switch Paris North (Project)

Claim 84922 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Capacity classification · It load

Actual · Global Switch Paris North (Project)

Claim 84923 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Capacity basis · 24 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Global Switch Paris North (Project)

Claim 84924 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Customer utilization · Not publicly disclosed

Actual · Global Switch Paris North (Project)

Claim 84925 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Identity boundary · This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios

Actual · Global Switch Paris North (Project)

Claim 84926 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch annual report and Paris campus record

    Global Switch Holdings Limited · Document date: Jun 1, 2024 · Primary

    Source reference: SRC-4778 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.es/wp-content/uploads/2025/08/Global-Switch-Holdings-Limited-Annual-Report-and-Financial-Statements-for-the-year-ended-31-December-2023.pdf

Source refresh date · 2026-08-29

Actual · Global Switch Paris North (Project)

Claim 84927 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Campus location · 7–9 Rue Petit, Clichy

Actual · Global Switch Paris North (Project)

Claim 84928 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch Paris North official profile

    Global Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3828 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.com/data-centres/paris/

Campus floor area · 50,000 square metres

Actual · Global Switch Paris North (Project)

Claim 84929 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Global Switch annual report and Paris campus record

    Global Switch Holdings Limited · Document date: Jun 1, 2024 · Primary

    Source reference: SRC-4778 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.globalswitch.es/wp-content/uploads/2025/08/Global-Switch-Holdings-Limited-Annual-Report-and-Financial-Statements-for-the-year-ended-31-December-2023.pdf

Counterparties and capital

Global Switch · Developer · CMP-1484

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.