Galaxy Data Center Banchang Rayong Campus

Ban Chang, Rayong, ThailandPreconstruction
Capacity
404 MW
Planned critical IT
Lead participant
Galaxy Data Center
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Galaxy Data Center Banchang Rayong Campus

Galaxy Data Center is developing an AI-focused campus in Ban Chang, Rayong. The company states a total design of 404 MW of IT load, with high-density liquid cooling and individual buildings designed to support at least 80 MW.

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load404 MWDesign · Galaxy Data Center Banchang Rayong Campus
It Load404 MWDesign · Galaxy Data Center Banchang Rayong Campus

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

Galaxy Data Center Banchang Rayong Campus: Preconstruction.

Galaxy Data Center Banchang Rayong Campus: Development-stage AI data center campus.
In Progress
Galaxy Data Center Banchang Rayong Campus — Preconstruction
In Progress

Infrastructure

Electric GridPlanned Or Represented

404 MW

404 MW planned or design IT capacity

Site FacilityPlanned Or Represented

High-density liquid cooling and dual AC/DC power-supply architecture.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Galaxy Data Center campus | Ban Chang | Rayong | Thailand
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
404 MW
Design
Capacity Basis
Source stated total campus IT load
Actual
Project Identity
Galaxy Data Center Banchang Rayong Campus
Actual
Lifecycle Status
Preconstruction
Actual
Location
Ban Chang, Rayong, TH
Actual
Participant Roles
Galaxy Data Center
Actual
Capacity
404 MW
Design
Capacity Basis
404 MW planned or design IT capacity
Actual
Development Scale
404 MW planned IT load; at least 80 MW per building
Actual
Infrastructure
High density liquid cooling and dual AC/DC power supply architecture.
Actual