Galaxy Data Center Banchang Rayong Campus
- Planned critical IT
- 404 MW
- Updated
- Oct 28, 2026
Galaxy Data Center is developing an AI-focused campus in Ban Chang, Rayong. The company states a total design of 404 MW of IT load, with high-density liquid cooling and individual buildings designed to support at least 80 MW.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Galaxy Data Center Banchang Rayong Campus: Preconstruction.
Milestones (2)
Date not disclosed · Event timing type not established
In progress · Announced
Source not linkedDate not disclosed · Event timing type not established
In progress · Status changed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Galaxy Data Center Thailand Project · Primary
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Planned or represented
404 MW
404 MW planned or design IT capacity
Planned or represented
High-density liquid cooling and dual AC/DC power-supply architecture.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.