Flexential Atlanta-Norcross 2

Norcross / Peachtree Corners, Georgia, United StatesPreconstruction
Evidence
Planned / design
4.5 MW
Updated
Oct 28, 2026

Flexential Atlanta-Norcross 2 is a planned data center at 2755 Northwoods Parkway, adjacent to but physically distinct from the company's existing Norcross facility. Flexential announced the project in April 2026 and expects it online in the first half of 2028. Current materials describe a 48,000-square-foot facility, while a facility guide separately identifies a 25,000-square-foot data center footprint. Norcross 2 is designed around 4.5 MW of critical-load UPS capacity, Georgia Power service, 4:3 distributed-redundant UPS, N+1 cooling, a target PUE of 1.3, zero-water-use design and a network backbone scalable to 400 Gbps.

Capacity

Critical load UPS capacity

Planned / design or future potential

4.5 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Norcross 2 planned facilityPlanned

1 building

Separate facility adjacent to Norcross 1.

Milestones (2)
Flexential announced Norcross 2

Apr 14, 2026 · Recorded actual event

Completed · Announced

Source not linked
Norcross 2 expected online in first half 2028

H1 2028 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Flexential

Developer · Operator

Sources by role

Site & development

Building area

Design

48,000 sq. ft.

Source

Technical specifications

Cooling redundancy

Design

N+1

Source

Water use target

Forecast

0 water use

Source

Additional project facts

Data center footprint

Design

25,000 sq. ft.

Source

UPS redundancy

Design

4:3 Distributed redundant

Source

Target PUE

Forecast

1.3 PUE

Source

Infrastructure & permits

Technical details (3)
Utility service

Secured or contracted

Georgia Power will serve Norcross 2.

Cooling system

Planned or represented

N+1 cooling redundancy with target PUE 1.3 and zero-water-use design.

Fiber

Planned or represented

400 Gbps

Network backbone scalable to 400 Gbps.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
Flexential Douglasville 1 Data Center

Operating · Douglasville, Georgia, United States

Shared participant: Flexential · Same market: Georgia, United States

Compare in a collection