Firebird Armenia AI Factory
- Planned critical IT
- 15 MW
- Updated
- Oct 28, 2026
Firebird launched the first phase of its Armenia AI Factory in Hrazdan in August 2026. The operator identifies 15 MW for the operating first facility and a roadmap to scale the Armenian platform substantially by the end of 2027. NVIDIA DSX reference design and high-density AI infrastructure.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Firebird Armenia AI Factory: Operating with expansion underway.
Milestones (2)
Aug 8, 2026 · Event timing type not established
In progress · Construction started
Source not linkedDate not disclosed · Event timing type not established
In progress · Status changed
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- Firebird Opens the Region’s Largest AI Factory · Aug 8, 2026 · Primary
Other participants (1)
Government authority
Sources by role
Government authority (1)
- Firebird Opens the Region’s Largest AI Factory · Aug 8, 2026 · Primary
Capital & incentives
Financing records
Construction loan
$60mMar 1, 2026
Ameriabank financing for construction of the Armenia AI factory.
Parties & sources
ePLDT (Sponsor)
Sources (2)
- Firebird Opens the Region’s Largest AI Factory · Aug 8, 2026
- Ameriabank finances Firebird AI data center · Mar 1, 2026
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Partially operational
15 MW
15 MW operating IT capacity
Partially operational
NVIDIA DSX reference design and high-density AI infrastructure.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.