Evolution TH01 Bang Na
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
- Utility
- Metropolitan Electricity Authority · Metropolitan Waterworks Authority
Evolution TH01 is a two-phase data centre development on Bang Na Trad Road in metropolitan Bangkok, developed with Central Pattana. Evolution specifies 12 MW of IT design capacity for Phase 1 and 40 MW for Phase 2, with service targets of Q4 2026 and Q2 2027 respectively. A hyperscaler has committed to Phase 1. IFC’s disclosure, updated 14 February 2026, lists a loan of up to $150 million as approved and pending signing. Its environmental review describes air cooling for Phase 1 and planned liquid cooling for Phase 2.
Capacity
Planned IT capacity MW
Planned / design or future potential12 MW
TH01 Phase 1 · Phase
Phase scope; not a whole-site figure
SourcePlanned IT capacity MW
Planned / design or future potential40 MW
TH01 Phase 2 · Phase
Phase scope; not a whole-site figure
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
12MW IT design; customer committed.
1 building
40MW IT design for AI workloads.
Milestones (4)
Dec 2024 · Recorded actual event
Completed · Construction started
Sources (1)
- 48198 - Evolution DC TH: Environmental & Social Review Summary · Nov 14, 2025 · Primary
Dec 15, 2025 · Recorded actual event
Completed · Financing
Sources (1)
- 48198 - Evolution Data Centres Thailand: Summary of Investment Information · Nov 14, 2025 · Primary
Q4 2026 · Forecast / planned record
Forecast · Forecast completion
Sources (1)
- Markets · Primary
Q2 2027 · Forecast / planned record
Forecast · Forecast completion
Sources (1)
- Markets · Primary
Participants
Investor
Sources by role
Investor (1)
- 48198 - Evolution Data Centres Thailand: Summary of Investment Information · Nov 14, 2025 · Primary
Owner
Sources by role
Owner (1)
- 48198 - Evolution DC TH: Environmental & Social Review Summary · Nov 14, 2025 · Primary
Other participants (2)
Utility provider
Sources by role
Utility provider (1)
- 48198 - Evolution DC TH: Environmental & Social Review Summary · Nov 14, 2025 · Primary
Utility provider
Sources by role
Utility provider (1)
- 48198 - Evolution DC TH: Environmental & Social Review Summary · Nov 14, 2025 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Debt financing
$150mDec 15, 2025
IFC board-approved loan ceiling; pending signing as of disclosure update 2026-02-14. Not disbursed funding.
Parties & sources
International Finance Corporation (Lender)
Sources (1)
Site & development
Additional project facts
Infrastructure & permits
Technical details (4)
Planned or represented
MEA is the planned project electricity supplier.
Planned or represented
MWA supply; Phase2 estimated demand 1,670m3/day.
Planned or represented
Phase1 air cooling; Phase2 liquid cooling.
Planned or represented
Eight network providers listed for TH01.
Project map
Other · Documented
TH01: ESIA not required (IFC assessment)
Nov 14, 2025
Sources (1)
- 48198 - Evolution DC TH: Environmental & Social Review Summary · Nov 14, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.