Equinix SV18 Silicon Valley Data Center

San Jose area, California, United StatesPartially operational
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Equinix is delivering SV18 in Silicon Valley in phases. Its 2025 annual report identifies phase 1 for the second quarter of 2026 and phase 2 for the second quarter of 2027, but does not disclose a defensible site MW total. Equinix is associated with the development in San Jose area, Santa Clara County, CA, US. The disclosed development scope includes phase 1 target Q2 2026; 2,100 sellable cabinets; Phase 2 target Q2 2027. Power and physical infrastructure include phased International Business Exchange data center development. Equinix does not publish a defensible SV18 facility MW total in its annual report. The available public sources do not establish a project-scoped operating or contracted capacity figure.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating and expansion programPartially operational

Project-wide phase for Equinix SV18 Silicon Valley Data Center; capacity class is unresolved.

Milestones (2)
Equinix SV18 development disclosed

Feb 11, 2026 · Recorded actual event

Completed · Announced

Source not linked
Phase 1 delivered in 2026; Phase 2 under development

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Equinix, Inc.

Operator

Sources by role
Operator (1)

Site & development

Location context

Actual

Equinix SV18 | Silicon Valley | California

Source

Location context

Actual

Equinix SV18 | Silicon Valley | California

Source

Development scale

Actual

Phase 1 target Q2 2026

Source

Development milestone

Actual

2,100 Sellable cabinets

Source

Site configuration

Actual

Equinix SV18 | Silicon Valley | California

Source

Technical specifications

Power arrangement

Actual

Phase 2 target Q2 2027.

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Lifecycle status

Actual

Partially operational

Source

Infrastructure & permits

Technical details (2)
Electric grid

Partially operational

Equinix does not publish a defensible SV18 facility MW total in its annual report.

Site facility

Partially operational

Phased International Business Exchange data center development.

Public-source research. Plans may change. See Evidence for sources and qualifications.