Equinix SG6

SingaporeUnder construction
Evidence
Planned / design
20 MW
Updated
Oct 28, 2026

Equinix broke ground on SG6 in November 2024. Its current 2025 annual filing still schedules Phase 1 for Q1 2027 with 1,550 cabinets, while the nine-story facility is planned to provide 20 MW when fully built.

Capacity

Full build power

Planned / design or future potential

20 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

SG6 Phase 1Under construction

1 building

Current filing supersedes the prior 1,525-cabinet table entry.

SG6 fully built facilityPlanned

1 building

Full-build power envelope, not Phase 1 operating capacity.

Milestones (2)
Equinix announces and breaks ground on SG6

Nov 19, 2024 · Recorded actual event

Completed · Construction started

Source not linked
SG6 Phase 1 target

Q1 2027 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Equinix, Inc.

Developer

Sources by role
Other participants (2)
Infocomm Media Development Authority

Government authority

Sources by role
Singapore Economic Development Board

Government authority

Sources by role
Government authority (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Phase 1 capex

Reported rounded

$290,000,000

Source

Initial investment announcement

Transaction scope

$260,000,000

Source

Financing records

Investment commitment

$260m

Nov 19, 2024

Initial SG6 investment announcement; not a project-financing close.

Parties & sources

Equinix, Inc. (Sponsor)

Investment commitment

$290m

Feb 11, 2026

Current Form 10-K estimate; may change with final construction details and is not a debt instrument.

Parties & sources

Equinix, Inc. (Sponsor)

Site & development

Building height

Design

9 stories

Source

Technical specifications

Liquid cooling capability

Forecast

Planned

Source

Renewable energy coverage

Actual

Operator says facility will be covered

Source

Additional project facts

Current status

Actual

Under construction; Phase 1 target Q1 2027

Source

Groundbreaking date

Actual

2024-11-19

Source

Phase 1 target rfs

Forecast

Q1 2027

Source

Phase 1 cabinet capacity

Actual

1,550 cabinets

Source

Pilot dc cfa status

Actual

Awarded

Source

Infrastructure & permits

Technical details (3)
Electric grid

Planned or represented

20 MW

Facility output when fully built; not Phase 1 live capacity.

Compute and platform system

Under construction

1,550 cabinets

Current Form 10-K development schedule.

Cooling system

Planned or represented

Planned support for high-power compute; no deployed customer configuration yet.

Other · Issued

Pilot Data Centre Call for Application award

Infocomm Media Development Authority

Nov 19, 2024