Cartis diligence evidence schedule

Equinix OS5x Osaka

PRJ-0551 · Site · Osaka, Japan

Record last updated Oct 28, 2026

Scope and capacity

Equinix lists OS5x as a new Osaka xScale data center planned for the first quarter of 2027. Its address, capacity, customer, capital allocation and construction start have not been publicly disclosed.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Official name · OS5x

Actual · Equinix OS5x Osaka (Project)

Claim 50509 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 13, 2026

  1. Expanding our global reach

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2658 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

Facility class · XScale data center

Actual · Equinix OS5x Osaka (Project)

Claim 50510 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 13, 2026

  1. Expanding our global reach

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2658 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

Location · Osaka, Japan

Actual · Equinix OS5x Osaka (Project)

Claim 50511 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 13, 2026

Conflicting public evidence is preserved.

  1. Expanding our global reach

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2658 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

Target opening · Q1 2027

Forecast · OS5x planned opening (Phase)

Claim 50512 · Recorded claim type: Forecast · Review: Approved · Claim date: Aug 13, 2026

Conflicting public evidence is preserved.

  1. Expanding our global reach

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2658 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

Boundary exclusion · Distinct from Osaka IBX and earlier Osaka xScale facilities

Actual · Equinix OS5x Osaka (Project)

Claim 50518 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 13, 2026

  1. Hyperscale connectivity drives data center projects by Equinix and JV partners

    Equinix · Document date: Mar 9, 2021 · Corroborating

    Source reference: SRC-2660 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2021-03-09-Hyperscale-Connectivity-Drives-3-Billion-in-Data-Center-Projects-by-Equinix-and-JV-Partners

  2. Equinix and GIC to form greater-than-US$1.0 billion Japan xScale joint venture

    Equinix · Document date: Apr 21, 2020 · Corroborating

    Source reference: SRC-2659 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2020-04-21-Equinix-and-GIC-to-Form-Greater-than-US-1-0-Billion-Joint-Venture-to-Develop-and-Operate-Hyperscale-Data-Centers-in-Japan

  3. Expanding our global reach

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2658 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

Counterparties and capital

Equinix, Inc. · Operator · CMP-0222

GIC · Investor · CMP-1265

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.