Scope and capacity

On August 11, 2026, Equinix said LG3 was scheduled to open later in 2026. This is a forecast, not a confirmed ready-for-service date; it is later than the earlier Q1 target and the Q2 target still shown on the expansion list, whose discrepancy should not be treated as proof of opening. Equinix is developing LG3 in Lagos, a USD22 million first-phase IBX facility with 225 sellable cabinets; ready-for-service remains not publicly disclosed. Equinix LG3 Lagos is located in 43 Saka Tinubu Street, Lagos, LA, NG and is a data center facility in construction status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Facility code · LG3

Actual · Equinix LG3 Lagos (Project)

Claim 38462 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

  2. Equinix 2025 Form 10-K

    Equinix / U.S. Securities and Exchange Commission · Document date: Not stated · Corroborating

    Source reference: SRC-0355 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm

  3. LG3 Lagos data center

    Equinix · Document date: Not stated · Corroborating

    Source reference: SRC-2142 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/br/pt/data-centers/europe-colocation/nigeria-colocation/lagos-data-centers/lg3

Facility address · 43 Saka Tinubu Street, Lagos 101241

Actual · Equinix LG3 Lagos (Project)

Claim 38463 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix plans USD22 million Lagos data center

    Data Center Dynamics · Document date: Nov 10, 2025 · Corroborating

    Source reference: SRC-2146 · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/equinix-plans-22-million-data-center-in-lagos-nigeria/

  2. LG3 Lagos data center

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2142 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/br/pt/data-centers/europe-colocation/nigeria-colocation/lagos-data-centers/lg3

Development status · —

Actual · Equinix LG3 Lagos (Project)

Claim 38464 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix 2025 Form 10-K

    Equinix / U.S. Securities and Exchange Commission · Document date: Not stated · Primary

    Source reference: SRC-0355 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm

  2. Data center expansion timeline

    Equinix · Document date: Not stated · Corroborating

    Source reference: SRC-2140 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

  3. Equinix LG3

    Data Center Map · Document date: Not stated · Corroborating

    Source reference: SRC-2147 · Recorded authority: Secondary

    Source URL

    https://www.datacentermap.com/nigeria/lagos/equinix-lg3/

Phase 1 capex · $22 million

Reported rounded · Equinix LG3 Lagos (Project)

Claim 38465 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

  2. Equinix 2025 Form 10-K

    Equinix / U.S. Securities and Exchange Commission · Document date: Not stated · Corroborating

    Source reference: SRC-0355 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm

Sellable cabinets · 225 cabinets

Reported rounded · Equinix LG3 Lagos (Project)

Claim 38466 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Equinix 2025 Form 10-K

    Equinix / U.S. Securities and Exchange Commission · Document date: Not stated · Primary

    Source reference: SRC-0355 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm

Current portfolio target open · 2026-Q2

Forecast · Equinix LG3 Lagos (Project)

Claim 38468 · Recorded claim type: Forecast · Review: Approved with conflict · Claim date: Not stated

  1. Data center expansion timeline

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2140 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

Ready for service verified · False

Actual · Equinix LG3 Lagos (Project)

Claim 38469 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Data center expansion timeline

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2140 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/expansions

  2. Lagos data centers

    Equinix · Document date: Not stated · Corroborating

    Source reference: SRC-2143 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/data-centers/europe-colocation/nigeria-colocation/lagos-data-centers

  3. Equinix LG3

    Data Center Map · Document date: Not stated · Corroborating

    Source reference: SRC-2147 · Recorded authority: Secondary

    Source URL

    https://www.datacentermap.com/nigeria/lagos/equinix-lg3/

First newly built equinix facility in west africa · True

Actual · Equinix LG3 Lagos (Project)

Claim 38470 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

Carrier neutral · True

Actual · Equinix LG3 Lagos (Project)

Claim 38471 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. LG3 Lagos data center

    Equinix · Document date: Not stated · Primary

    Source reference: SRC-2142 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/br/pt/data-centers/europe-colocation/nigeria-colocation/lagos-data-centers/lg3

Equinix fabric planned · True

Actual · Equinix LG3 Lagos (Project)

Claim 38472 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

Building stories · 4 stories

Reported rounded · Equinix LG3 Lagos (Project)

Claim 38473 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Equinix plans USD22 million Lagos data center

    Data Center Dynamics · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2146 · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/equinix-plans-22-million-data-center-in-lagos-nigeria/

Reported floor area · 610 square meters

Reported rounded · Equinix LG3 Lagos (Project)

Claim 38474 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Equinix plans USD22 million Lagos data center

    Data Center Dynamics · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2146 · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/equinix-plans-22-million-data-center-in-lagos-nigeria/

Acquired with mainone · False

Actual · Equinix LG3 Lagos (Project)

Claim 38475 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Corroborating

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

  2. Equinix Form 10-Q — MainOne acquisition accounting

    Equinix · Document date: Jul 29, 2022 · Corroborating

    Source reference: SRC-2145 · Regulatory record

    Source URL

    https://investor.equinix.com/sec-filings/all-sec-filings/content/0001628280-22-019818/eqix-20220630.htm

  3. Equinix closes MainOne acquisition

    Equinix · Document date: Apr 5, 2022 · Primary

    Source reference: SRC-2144 · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2022-04-05-Equinix-Enters-Africa%2C-Closing-the-US-320-Million-Acquisition-of-MainOne

Operating IT capacity disclosed · False

Actual · Equinix LG3 Lagos (Project)

Claim 38478 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

  2. Equinix 2025 Form 10-K

    Equinix / U.S. Securities and Exchange Commission · Document date: Not stated · Corroborating

    Source reference: SRC-0355 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm

  3. LG3 Lagos data center

    Equinix · Document date: Not stated · Corroborating

    Source reference: SRC-2142 · Recorded authority: Party primary

    Source URL

    https://www.equinix.com/br/pt/data-centers/europe-colocation/nigeria-colocation/lagos-data-centers/lg3

Tenant disclosed · False

Actual · Equinix LG3 Lagos (Project)

Claim 38479 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Equinix announces new USD22 million data center in Lagos

    Equinix · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2141 · Company announcement · Recorded authority: Party primary

    Source URL

    https://newsroom.equinix.com/2025-11-10-Equinix-Announces-Plans-for-New-22-Million-Data-Center-in-Lagos%2C-Nigeria

  2. Equinix 2025 Form 10-K

    Equinix / U.S. Securities and Exchange Commission · Document date: Not stated · Corroborating

    Source reference: SRC-0355 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm

Counterparties and capital

Equinix, Inc. · Developer · CMP-0222

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.