Entergy Waterford Unit 5

PRJ-0232 · Site · Waterford site, Louisiana, United States

Record last updated Oct 28, 2026

Scope and capacity

Entergy reports that site preparation for Waterford Unit 5 began in November 2025, with main construction scheduled for late 2026 and completion expected in 2029. This is site preparation, not confirmation that main construction has started. New combined-cycle unit at Entergy's existing Waterford generation site; generation asset, not a data-center campus. Entergy Waterford Unit 5 is in Waterford site, LA, US and is a generation site with preconstruction status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Target service date · 2029-12-31

Source report · Entergy Waterford Unit 5 (Project)

Claim 22452 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Project Evest generation planning testimony

    Entergy Louisiana · Document date: Mar 25, 2026 · Corroborating

    Source reference: SRC-1256

    Source URL

    https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/ViewFile?fileId=uX0tgxxqZ6k%3D

  2. Meta keeps buying Rosemount land

    KSTP · Document date: Oct 15, 2025 · Corroborating

    Source reference: SRC-0789 · News report · Recorded authority: Secondary

    Source URL

    https://kstp.com/kstp-news/local-news/facebook-parent-meta-keeps-buying-rosemount-land/

  3. Meta buys more Rosemount land for potential expansion

    Data Center Dynamics · Document date: Feb 22, 2025 · Corroborating

    Source reference: SRC-0788 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/meta-buys-more-land-in-rosemount-minnesota-for-data-center-project/

  4. Development in Rosemount: Meta data center

    City of Rosemount · Document date: Not stated · Primary

    Source reference: SRC-0784 · Government record · Recorded authority: Official primary

    Source URL

    https://www.rosemountmn.gov/920/Development-in-Rosemount

Counterparties and capital

Entergy Louisiana · Utility provider · CMP-0640

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.