Eneus Energy - Harlingen

Harlingen, Texas, United StatesProposed
Evidence
Planned / design
2,000 MW
Updated
Oct 28, 2026

Eneus Energy’s Harlingen proposal is a long-range, energy-integrated data center campus on roughly 1,785 acres in Cameron County, Texas. Eneus describes as many as 16 data halls, up to 2 GW of total power, a planned 765 kV connection, closed-cycle cooling using reclaimed wastewater and more than $14 billion of capital investment through 2045. The 2 GW amount is a prospective full-build power envelope, not operating capacity. Final customers, permits, utility agreements, generation mix, incentives and phase financing remain uncommitted.

Capacity

Reported capacity

Planned / design or future potential

2,000 MW

Source

Reported capacity

Planned / design or future potential

2,000 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Long-range master planning and utility evaluationAnnounced or preconstruction

Eneus Energy’s Harlingen proposal is a long-range, energy-integrated data center campus on roughly 1,785 acres in Cameron County, Texas. Eneus describes as many as 16 data halls, up to 2 GW of total power, a planned 765 kV connection, closed-cycle cooling using reclaimed wastewater and more than $14 billion of capital investment through 2045. The 2 GW amount is a prospective full-build power envelope, not operating capacity. Final customers, permits, utility agreements, generation mix, incentives and phase financing remain uncommitted.

Participants

Eneus Energy

Developer

Sources by role
Developer (1)

Capital & incentives

Capital claims

Reported investment

Reported rounded

$14,000,000,000

Source

Site & development

Location context

Actual

Eneus Energy - Harlingen | Harlingen | Texas | US

Source

Location context

Actual

Eneus Energy - Harlingen | Harlingen | Texas | US

Source

Site area

Actual

1,785 acres

Source

Development horizon

Forecast

2045

Source

Additional project facts

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

2,000 MW future full build site capacity; not measured operating IT load.

Source

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

Up to 2,000 MW is the long range full build campus power envelope.

Source

Data hall count

Actual

16 data halls

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

2,000 MW

Planned 765 kV connection and full-build campus envelope.

Water

Planned or represented

Closed-cycle cooling using reclaimed wastewater.

Public-source research. Plans may change. See Evidence for sources and qualifications.