Scope and capacity
Elea operates SPO3 in Tamboré after acquiring the facility from DXC in 2024. Elea describes future expansion for AI and enterprise demand but does not disclose a site-specific live or future MW figure.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (3)
Current status · Operational; expansion planned
Actual · Elea SPO3 Tamboré (Project)
Claim 53298 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SPO3 Tamboré
Elea Data Centers · Document date: Not stated · Primary
Source reference: SRC-2871 · Fact sheet · Recorded authority: Party primary
Source URL
https://eleadatacenters.com/en/datacenters/spo3-tambore/
https://eleadatacenters.com/en/datacenters/spo3-tambore/
Acquired from · DXC Technology
Transaction scope · Elea SPO3 Tamboré (Project)
Claim 53299 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Jul 16, 2024
- Elea Digital Data Centers announces 120MW footprint expansion in the Greater São Paulo area
Elea Data Centers · Document date: Jul 16, 2024 · Primary
Source reference: SRC-2869 · Company announcement · Recorded authority: Party primary
Source URL
https://eleadatacenters.com/en/2024/07/16/elea-digital-data-centers-announces-120mw-footprint-expansion-in-the-greater-sao-paulo-area/
https://eleadatacenters.com/en/2024/07/16/elea-digital-data-centers-announces-120mw-footprint-expansion-in-the-greater-sao-paulo-area/
- Piemonte Holding reports acquisition of São Paulo data centers
Piemonte Holding · Document date: Jul 8, 2024 · Corroborating
Source reference: SRC-6696 · Company announcement · Recorded authority: Party primary
Source URL
https://www.piemonteholding.com/2024/07/08/piemonte-holding-expande-atuacao-no-brasil-com-nova-aquisicoes-de-data-centers/
https://www.piemonteholding.com/2024/07/08/piemonte-holding-expande-atuacao-no-brasil-com-nova-aquisicoes-de-data-centers/
Certified renewable energy · Operator claim
Actual · Elea SPO3 Tamboré (Project)
Claim 53303 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SPO3 Tamboré
Elea Data Centers · Document date: Not stated · Primary
Source reference: SRC-2871 · Fact sheet · Recorded authority: Party primary
Source URL
https://eleadatacenters.com/en/datacenters/spo3-tambore/
https://eleadatacenters.com/en/datacenters/spo3-tambore/
Counterparties and capital
DXC Technology · Owner · CMP-1360
Elea Data Centers · Operator · CMP-1196
I Squared Capital · Investor · CMP-1255
Piemonte Holding · Investor · CMP-1361