Cartis diligence evidence schedule

EDGNEX Jakarta AI Data Center Campus

PRJ-0712 · Site · Jakarta, Jakarta metropolitan area, Indonesia

Record last updated Oct 28, 2026

Scope and capacity

EDGNEX by DAMAC is developing a hyperscale data-center campus in Greater Jakarta. The announced campus design totals 144 MW. EDGNEX by DAMAC is associated with the development in Jakarta, Greater Jakarta, Jakarta metropolitan area, ID. The disclosed development scope includes 144 MW planned campus; hyperscale and AI-ready design; Greater Jakarta market. Power and physical infrastructure include phased hyperscale campus serving Indonesia’s cloud and AI market. EDGNEX describes a 144 MW Jakarta campus design.

Headline: 144 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · EDGNEX campus | Greater Jakarta | Indonesia

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 57988 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Lifecycle status · Preconstruction

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 57989 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Reported capacity · 144 MW

Planned / design or future potential · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 57990 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Capacity basis · EDGNEX describes a 144 MW Jakarta campus design.

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 57991 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Location context · EDGNEX campus | Greater Jakarta | Indonesia

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111455 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Lifecycle status · Preconstruction

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111456 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Reported capacity · 144 MW

Planned / design or future potential · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111457 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Capacity basis · EDGNEX describes a 144 MW Jakarta campus design.

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111458 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Development scale · 144 MW planned campus

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111475 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Indonesia digital ministry investment statement

    Ministry of Communication and Digital Affairs of Indonesia · Document date: Jun 19, 2025 · Corroborating

    Source reference: SRC-6258 · Government record · Recorded authority: Official primary

    Source URL

    https://portal.komdigi.go.id/kanal-publik/berita-kini/9428

  2. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Development milestone · Hyperscale and AI-ready design

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111476 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Indonesia digital ministry investment statement

    Ministry of Communication and Digital Affairs of Indonesia · Document date: Jun 19, 2025 · Corroborating

    Source reference: SRC-6258 · Government record · Recorded authority: Official primary

    Source URL

    https://portal.komdigi.go.id/kanal-publik/berita-kini/9428

  2. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Power arrangement · Greater Jakarta market.

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111477 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Indonesia digital ministry investment statement

    Ministry of Communication and Digital Affairs of Indonesia · Document date: Jun 19, 2025 · Corroborating

    Source reference: SRC-6258 · Government record · Recorded authority: Official primary

    Source URL

    https://portal.komdigi.go.id/kanal-publik/berita-kini/9428

  2. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Site configuration · EDGNEX campus | Greater Jakarta | Indonesia

Actual · EDGNEX Jakarta AI Data Center Campus (Project)

Claim 111478 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Indonesia digital ministry investment statement

    Ministry of Communication and Digital Affairs of Indonesia · Document date: Jun 19, 2025 · Corroborating

    Source reference: SRC-6258 · Government record · Recorded authority: Official primary

    Source URL

    https://portal.komdigi.go.id/kanal-publik/berita-kini/9428

  2. EDGNEX announces Jakarta data center campus

    EDGNEX by DAMAC · Document date: Jan 22, 2024 · Primary

    Source reference: SRC-3176 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.edgnex.com/

Counterparties and capital

EDGNEX by DAMAC · Developer · CMP-1452

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.