EdgeConneX Kyotanabe AI Campus

Kyotanabe / Greater Osaka, Japan · 26Under construction
Evidence
Planned / design
200 MW
Updated
Oct 28, 2026

One Kyotanabe campus developed with Kagoya; excludes the separate Yawata campus and wider 350 MW regional plan. EdgeConneX Kyotanabe AI Campus is in Kyotanabe / Greater Osaka, 26, JP and is a data center campus with under construction status.

Capacity

Campus planned power capacity

Planned / design or future potential

200 MW

Source

Initial phase capacity

Planned / design or future potential

28 MW

Source

Later marketed additional capacity

Planned / design or future potential

114 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Kyotanabe initial phase / ITM01Under construction

1 building

First phase; source terminology does not consistently resolve IT versus utility power.

Kyotanabe later marketed expansionPlanned

1 building

The location page describes a later 114-MW expansion.

Milestones (3)
EdgeConneX announces Japanese market entry

Jan 13, 2025 · Recorded actual event

Completed · Announced

Source not linked
Construction announced at Kyotanabe

Mar 17, 2026 · Recorded actual event

Completed · Construction started

Source not linked
Initial 28 MW phase targeted for Q1 2028

Q1 2028 · Forecast / planned record

Forecast · Event type not stated

Source not linked

Participants

EdgeConneX

Developer · Operator

Sources by role
Developer / Operator (1)
Developer / Operator (1)
Other participants (1)
Kyotanabe City

Government authority

Sources by role
Government authority (1)
Government authority (1)

Site & development

Site area

Actual

130,000 square metres

Source

Construction commenced date

Actual

2026-03-17

Source

Technical specifications

Liquid cooling capable

Source report

True

Source

Additional project facts

Initial service target

Actual

2028-Q1

Source

High density AI ready

Source report

True

Source

Distance from central osaka

Actual

30 kilometres

Source

Customer identity public

Source report

False

Source

Utility identity public

Source report

False

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

200 MW

Company-announced campus power capacity; utility and IT definition not published.

Cooling system

Planned or represented

AI/high-density infrastructure designed to support liquid cooling.

Public-source research. Plans may change. See Evidence for sources and qualifications.