Cartis diligence evidence schedule
EcoDataCenter Kvarnsveden Campus
PRJ-0478 · Site · Borlänge, W, Sweden
Captured 2026-09-06T04:13:04.416Z · Record last updated 2026-08-25
SHA-256: a6d16b7f6fd3c8ed8ec1b2ba6e8e5c287b7e779ee979057ccbf04648ddfb0331
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
EcoDataCenter Kvarnsveden Campus occupies the former Kvarnsveden paper-mill site and additional land. The announced scope is 250 MW at launch with potential to scale to 600 MW; both figures describe site power rather than operating IT capacity.
Headline: 600 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Launch Power Access · 250 MW
Source report · EcoDataCenter Kvarnsveden Campus (project)
Claim 45915 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556
Potential Full Scale · 600 MW
Planned / design or future potential · EcoDataCenter Kvarnsveden Campus (project)
Claim 45916 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556
Construction Started · 2025-09-24
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45919 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556
Former Use · Kvarnsveden paper mill
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45920 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556 - Roschier advised EcoDataCenter in acquisition of former Kvarnsveden paper mill
Roschier · Document date: 2024-09-09 · Primary
https://www.roschier.com/newsroom/roschier-has-advised-ecodatacenter-in-the-acqiuisition-of-parts-of-the-old-kvarnsveden-paper-mill-from-the-municipality-of-borlange
Site Acquired · 2,024
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45921 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556 - Roschier advised EcoDataCenter in acquisition of former Kvarnsveden paper mill
Roschier · Document date: 2024-09-09 · Primary
https://www.roschier.com/newsroom/roschier-has-advised-ecodatacenter-in-the-acqiuisition-of-parts-of-the-old-kvarnsveden-paper-mill-from-the-municipality-of-borlange
Site Area · 20 hectares approximate
Source report · EcoDataCenter Kvarnsveden Campus (project)
Claim 45922 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on Borlänge, Sweden data center
Data Center Dynamics · Document date: 2025-09-25 · Primary
https://www.datacenterdynamics.com/en/news/ecodatacenter-breaks-ground-on-borl%C3%A4nge-sweden-data-center/
Additional Land Agreement · Exclusive agreement to acquire
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45923 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556
Full Buildout Horizon · 8–10 Years
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45924 · Review: Approved · Claim date: Not published
- EcoDataCenter begins construction of mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-pbrjar-byggandet-av-megacampus-i-borlnge-3406557
Construction Partner · ByggPartner
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45925 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on Borlänge, Sweden data center
Data Center Dynamics · Document date: 2025-09-25 · Primary
https://www.datacenterdynamics.com/en/news/ecodatacenter-breaks-ground-on-borl%C3%A4nge-sweden-data-center/
Reported Land Acquisition Price · 400 SEK million
Source report · EcoDataCenter Kvarnsveden Campus (project)
Claim 45926 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on Borlänge, Sweden data center
Data Center Dynamics · Document date: 2025-09-25 · Primary
https://www.datacenterdynamics.com/en/news/ecodatacenter-breaks-ground-on-borl%C3%A4nge-sweden-data-center/
Owner · Areim
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45927 · Review: Approved · Claim date: Not published
- Areim-owned EcoDataCenter secures SEK 6.7 billion debt financing
Areim · Document date: 2025-09-09 · Primary
https://www.mynewsdesk.com/areim/pressreleases/areim-aegda-ecodatacenter-har-saekrat-skuldfinansiering-om-67-miljarder-kronor-foer-att-expandera-verksamheten-3430425 - EcoDataCenter accelerates growth journey with EUR 450 million in new funding
EcoDataCenter · Document date: 2025-03-05 · Primary
https://ecodatacenter.tech/press/ecodatacenter-accelerates-growth-journey-with-eur-450-million-in-new-funding-3372578
Customer Identity · Undisclosed
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45930 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556
Utility Identity · Undisclosed
actual · EcoDataCenter Kvarnsveden Campus (project)
Claim 45931 · Review: Approved · Claim date: Not published
- EcoDataCenter breaks ground on mega campus in Borlänge
EcoDataCenter · Document date: 2025-09-24 · Primary
https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556
Counterparties and capital
Borlänge Municipality · Landowner · CMP-1177
ByggPartner · Contractor · CMP-1178
Deutsche Bank · Lender · CMP-0383
Export Development Canada · Operator · CMP-1132
€450,000,000 · 2025-03-05
Areim capital for EcoDataCenter growth; no site allocation.
Areim (Capital Sponsor) · Export Development Canada (Capital Recipient / Operating Platform)
Financing record 138; claim-specific source links appear in the exhibit sources where published.
€600,000,000 · 2025-09-09
Deutsche Bank debt supporting EcoDataCenter expansion including Falun and Borlänge; no project allocation.
Deutsche Bank (Lender) · Export Development Canada (Borrower / Financed Platform)
Financing record 139; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.