Digital Realty ICN11 Digital Seoul 2
- Planned critical IT
- 80 MW
- Updated
- Oct 28, 2026
Digital Realty's public project update, checked October 28, 2026, reports that ICN11 had topped out and targets operation by the second half of 2027. Topping-out is not commissioning; no exact event day or new contract-value revision is inferred. Digital Realty's ICN11, also called Digital Seoul 2, is a 64 MW IT-load data center under construction in Gimpo. A Korean exchange filing places the construction period from May 2025 through October 2027 and records a corrected KRW 444.5 billion contract value.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Historical target retained for schedule lineage and not treated as RFS.
1 building
Current contract phase; completion target is not an achieved opening.
Milestones (6)
Jul 29, 2021 · Recorded actual event
Completed · Announced
Source not linked2023 · Event timing type not established
Cancelled · Forecast completion
Source not linkedMay 12, 2025 · Recorded actual event
Completed · Customer commitment
Source not linkedMay 25, 2025 · Recorded actual event
Completed · Construction started
Source not linkedMay 20, 2026 · Recorded actual event
Completed · Status changed
Source not linkedOct 24, 2027 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Operator
Sources by role
Operator (1)
Operator (1)
- Seoul Data Center & Colocation · Corroborating
Other participants (4)
Contractor
Sources by role
Contractor (1)
- Corrected single sales and supply contract — ICN11 Data Center · May 20, 2026 · Primary
Contractor
Sources by role
Contractor (1)
- Corrected single sales and supply contract — ICN11 Data Center · May 20, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Gimpo Hyperscale Data Center Clears Local Opposition, Finally Breaks Ground · May 14, 2025 · Primary
Government authority
Sources by role
Government authority (1)
- Gimpo Hyperscale Data Center Clears Local Opposition, Finally Breaks Ground · May 14, 2025 · Primary
Capital & incentives
Financing records
Commercial contract
₩444,504,218,768May 20, 2026
Current corrected contract amount, excluding VAT, payable monthly by progress. It is a construction contract value, not evidence of project-level debt financing.
Parties & sources
Digital Seoul 2 Ltd. (Other) · DL E&C (Other)
Sources (1)
Site & development
Construction contract value
Transaction scope444,504,218,768 KRW
Current ICN11 construction · Phase
SourceTechnical specifications
Additional project facts
Infrastructure & permits
Technical details (4)
Under construction
64 MW IT
Current regulated filing explicitly labels the facility as IT Load 64 MW.
Planned or represented
80 MW electrical
Secondary project report distinguishes 80 MW electrical capacity from 64 MW IT load.
Under construction
154 kV
Resident and permitting dispute concerned the extra-high-voltage connection; obtain utility records before verified publication.
Planned or represented
Secondary report says ICN11 is intended to connect by fiber to ICN10; route and service date undisclosed.
Project map
Building · Issued
ICN11
Gimpo City
Dec 31, 2021
Sources (1)
- Gimpo Hyperscale Data Center Clears Local Opposition, Finally Breaks Ground · May 14, 2025 · Primary
Other · Issued
ICN11
Gyeonggi Provincial Administrative Appeals Commission
Oct 31, 2024
Sources (1)
- Gimpo Hyperscale Data Center Clears Local Opposition, Finally Breaks Ground · May 14, 2025 · Primary
Other · Denied
ICN11
Gimpo City
Nov 17, 2024
Sources (1)
- Gimpo Hyperscale Data Center Clears Local Opposition, Finally Breaks Ground · May 14, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.