DCI Indonesia H2 Karawang Campus
- Planned critical IT
- 600 MW
- Updated
- Oct 28, 2026
DCI Indonesia's H2 campus has two live facilities. H2-01 has operated since November 2021; H2-02 was inaugurated in June 2023; DCI's current page reports 30 MW total IT load and at least 600 MW of long-term scalability.
Capacity
Solar pv potential
Planned / design or future potential30 MW
Generation capacity; not IT capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Facility-specific capacity is directly stated.
1 building
Standalone H2-02 IT capacity has not been publicly disclosed; the campus-level 12 MW figure is not assigned to H2-02.
86-hectare long-term envelope; not delivered capacity.
Milestones (2)
Nov 2021 · Recorded actual event
Completed · Commercial operation
Source not linkedJun 22, 2023 · Recorded actual event
Completed · Commercial operation
Source not linkedParticipants
Owner
Sources by role
Owner (1)
- DCI Indonesia and Salim Group inaugurate second data center in Karawang · Jun 22, 2023 · Primary
Operator
Sources by role
Operator (1)
- DCI Indonesia and Salim Group inaugurate second data center in Karawang · Jun 22, 2023 · Corroborating
Operator (1)
- Data Centers · Primary
Site & development
Additional project facts
Infrastructure & permits
Technical details (4)
Operational
30 MW
Current combined H2-01 and H2-02 total.
Reported context
27 MW
Combined campus state at the June 2023 H2-02 inauguration.
Partially operational
600 MW IT
At least 600 MW scalable potential; not delivered capacity.
Planned or represented
30 MW generation
Solar-generation potential across roughly 30 hectares; not IT load.
Project map