DCI Indonesia H2 Karawang Campus

Pertiwi Lestari Industrial Estate, Karawang, JB, IndonesiaPartially operational
Evidence
Planned critical IT
600 MW
Updated
Oct 28, 2026

DCI Indonesia's H2 campus has two live facilities. H2-01 has operated since November 2021; H2-02 was inaugurated in June 2023; DCI's current page reports 30 MW total IT load and at least 600 MW of long-term scalability.

Capacity

Current total IT load

Actual

30 MW

Not included in reviewed operating IT capacity

Source

H2 01 IT capacity

Actual

15 MW

Source

Future IT capacity potential

Planned / design or future potential

600 MW

Source

Solar pv potential

Planned / design or future potential

30 MW

Generation capacity; not IT capacity

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

H2-01Operational

1 building

Facility-specific capacity is directly stated.

H2-02Operational

1 building

Standalone H2-02 IT capacity has not been publicly disclosed; the campus-level 12 MW figure is not assigned to H2-02.

H2 full campus potentialOperational

86-hectare long-term envelope; not delivered capacity.

Milestones (2)
H2-01 operations begin

Nov 2021 · Recorded actual event

Completed · Commercial operation

Source not linked
DCI and Salim Group inaugurate H2-02

Jun 22, 2023 · Recorded actual event

Completed · Commercial operation

Source not linked

Participants

PT DCI Indonesia Tbk

Operator

Sources by role
Operator (1)
Operator (1)

Site & development

Site area

Actual

86 hectares

Source

Location

Actual

Pertiwi Lestari Industrial Estate, Karawang

Source

Additional project facts

Live facility count

Actual

2 facilities

Source

H2 01 opening

Actual

2021-11

Source

H2 02 opening

Actual

2023-06-22

Source

Asset partner

Actual

DISM, part of Salim Group

Source

Infrastructure & permits

Technical details (4)
Electric grid

Operational

30 MW

Current combined H2-01 and H2-02 total.

Electric grid

Reported context

27 MW

Combined campus state at the June 2023 H2-02 inauguration.

Electric grid

Partially operational

600 MW IT

At least 600 MW scalable potential; not delivered capacity.

Solar

Planned or represented

30 MW generation

Solar-generation potential across roughly 30 hectares; not IT load.

Public-source research. Plans may change. See Evidence for sources and qualifications.