DayOne Chonburi Tech Park 2

PRJ-0408 · Site · Chonburi, Thailand

Record last updated Oct 28, 2026

Scope and capacity

CTP2 is a prospective Chonburi growth zone under a DayOne-Amata memorandum of understanding. DayOne Chonburi Tech Park 2 is located in Chonburi, TH and is a data center campus in preconstruction status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Mou announcement date · 2025-11-10

Actual · DayOne Chonburi Tech Park 2 (Project)

Claim 37618 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. DayOne and Amata expand Chonburi toward 1 GW

    DayOne · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2115 · Company announcement · Recorded authority: Party primary

    Source URL

    https://dayonedc.com/headliners/dayone-strengthens-thailands-digital-hub-with-amata-as-chonburi-campus-expands-toward-the-countrys-first-1gw-power-platform

  2. Amata confirms Chonburi expansion and 1 GW platform

    Amata Corporation · Document date: Nov 10, 2025 · Corroborating

    Source reference: SRC-2117 · Recorded authority: Party primary

    Source URL

    https://amata.com/news/50-business-news/1385-dayone-strengthens-thailands-digital-hub-with-amata-as-chonburi-campus-expands-toward-the-countrys-first-1gw-power-platform

Development status · Memorandum of understanding

Actual · DayOne Chonburi Tech Park 2 (Project)

Claim 37619 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. DayOne and Amata expand Chonburi toward 1 GW

    DayOne · Document date: Nov 10, 2025 · Primary

    Source reference: SRC-2115 · Company announcement · Recorded authority: Party primary

    Source URL

    https://dayonedc.com/headliners/dayone-strengthens-thailands-digital-hub-with-amata-as-chonburi-campus-expands-toward-the-countrys-first-1gw-power-platform

  2. Amata confirms Chonburi expansion and 1 GW platform

    Amata Corporation · Document date: Nov 10, 2025 · Corroborating

    Source reference: SRC-2117 · Recorded authority: Party primary

    Source URL

    https://amata.com/news/50-business-news/1385-dayone-strengthens-thailands-digital-hub-with-amata-as-chonburi-campus-expands-toward-the-countrys-first-1gw-power-platform

Counterparties and capital

Amata Corporation · Landowner · CMP-1005

DayOne Data Centers · Developer · CMP-0071

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.